12244 W HATTERAS ST 91607
Certificate Information: 12244 W HATTERAS ST 91607
- Application / Permit
- 22014-20000-03252
- Plan Check / Job No.
- B22VN10099
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 19'-3" X 25'-3" ADDITION TO AND CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
- Permit Issued
- Issued on 2/9/2023
- Issuing Office
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 7/9/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/12/2022 | APPLICANT |
| Applicant returned to address corrections | 2/3/2023 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 2/7/2023 | SERGIO MUNIZ |
| Plan Check Approved | 2/8/2023 | PINANK PATEL |
| Plan Check Approved | 2/8/2023 | PINANK PATEL |
| Issued | 2/9/2023 | APPLICANT |
| CofO in Progress | 10/9/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 10/15/2024 | DANIEL ORRANTE |
| CofO Issued | 10/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2022 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 7/28/2022 | CHRIS CHAHBAZ |
| Construction near power lines | Cleared | 2/3/2023 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 2/7/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/14/2023 | Approved | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 7/14/2023 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 7/14/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/12/2023 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 9/14/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 9/18/2023 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 9/18/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 9/22/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 9/22/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/3/2023 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 10/3/2023 | Conditional Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/11/2023 | No Access for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/11/2023 | No Access for Inspection | CHRISTOPHER ROJAS |
| Insulation | 10/18/2023 | Approved | KIRK SANDERS |
| Shower Pan | 10/18/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/4/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 10/4/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 10/4/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 10/4/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/4/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 10/4/2024 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 10/4/2024 | Approved | OGANES TARAKHCHYAN |