6325 N ORION AVE 91411

Certificate Information: 6325 N ORION AVE 91411

Application / Permit
22014-20000-03242
Plan Check / Job No.
B22VN10054
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 13'-4" X 17'-6" ADDITION TO THE (E) SFD, (N) 4'-6" X 6' FRONT PORCH, INTERIOR REMODEL AND RE-ROOF THE (E) PATIO.
Permit Issued
Issued on 8/25/2022
Issuing Office
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 PINANK PATEL
Corrections Issued 7/2/2022 PINANK PATEL
Building Plans Picked Up 7/8/2022 APPLICANT
Plan Check Approved 8/25/2022 ALEC MOUSAKHANIAN
Issued 8/25/2022 APPLICANT
CofO in Progress 11/17/2023 RYAN SALAZAR
Permit Finaled 4/15/2024 DANIEL ORRANTE
CofO Issued 4/15/2024 DANIEL ORRANTE
Permit Finaled 4/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/5/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/19/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/9/2022 Approved RICHARD DOCKUS
Footing/Foundation/Slab 10/8/2022 Partial Approval RAUL OLAGI
Deputy Drilled-In Anchors 10/12/2022 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 10/14/2022 Approved MICHEL ABAJAN
Deputy Reinf. Concrete 10/19/2022 Conditional Approval DAVID MATSON
Wood Frame 10/25/2022 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Conditional Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 Not Ready for Inspection JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 12/6/2022 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 12/21/2022 No Access for Inspection RYAN SALAZAR
HVAC-Rough 12/21/2022 No Access for Inspection RYAN SALAZAR
PLUMBING-Rough 12/21/2022 No Access for Inspection RYAN SALAZAR
ELECTRICAL-Rough 12/22/2022 Approved JOHN COLEMAN
HVAC-Rough 12/22/2022 Approved JOHN COLEMAN
PLUMBING-Rough 12/22/2022 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 12/23/2022 Approved JOHN COLEMAN
HVAC-Rough 12/23/2022 Approved JOHN COLEMAN
Insulation 12/23/2022 Approved JOHN COLEMAN
PLUMBING-Rough 12/23/2022 Approved JOHN COLEMAN
Drywall Nailing 12/27/2022 Approved RYAN SALAZAR
Shower Pan 12/27/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/30/2022 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 2/16/2023 Approved JUSTIN HAWLEY
PLUMBING-Rough 3/9/2023 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 8/16/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 8/16/2023 Approved RYAN SALAZAR
Final 8/16/2023 Corrections Issued RYAN SALAZAR
Green Building Final 8/16/2023 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 8/16/2023 Approved RYAN SALAZAR
HVAC-Final 8/16/2023 Approved RYAN SALAZAR
MERV13>=Final 8/16/2023 Approved RYAN SALAZAR
MERV13>=Rough 8/16/2023 Approved RYAN SALAZAR
PLUMBING-Final 8/16/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 8/16/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 8/16/2023 Approved RYAN SALAZAR
Final 11/17/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 11/17/2023 Approved RYAN SALAZAR