8338 S DELGANY AVE 90293
Certificate Information: 8338 S DELGANY AVE 90293
- Application / Permit
- 22014-20000-03227
- Plan Check / Job No.
- B22VN10022
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING ATTACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | SELLA BENYAMIN |
| Corrections Issued | 7/25/2022 | SELLA BENYAMIN |
| Quality Review Completed | 7/25/2022 | STEVEN KIM |
| Building Plans Picked Up | 7/27/2022 | APPLICANT |
| Applicant returned to address corrections | 9/22/2022 | SELLA BENYAMIN |
| Plan Check Approved | 12/27/2022 | SELLA BENYAMIN |
| Issued | 12/27/2022 | APPLICANT |
| CofO in Progress | 10/1/2024 | BOBBY KEY |
| Permit Finaled | 11/21/2024 | RICHARD STEINBACH |
| CofO Issued | 11/21/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/21/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | JENSON LEE |
| Address approval | Cleared | 8/15/2022 | JENSON LEE |
| Sewer availability | Cleared | 8/18/2022 | ANTHONY MAINEZ |
Contact Information
| Contractor | Green Works Construction & Design Inc; Lic. No.: 936962-B | 20301 VENTURA BLVD #222 WOODLAND HILLS, CA 91364 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/13/2023 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 2/13/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 2/13/2023 | Partial Approval | BOBBY KEY |
| Pre-Inspection | 4/25/2023 | Partial Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 6/14/2023 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 6/14/2023 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 6/14/2023 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 6/14/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 6/20/2023 | Partial Approval | BOBBY KEY |
| Green Building Rough | 6/20/2023 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 6/20/2023 | Not Ready for Inspection | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 6/20/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 7/3/2023 | Approved | BOBBY KEY |
| Green Building Rough | 7/3/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 7/3/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 7/3/2023 | Approved | BOBBY KEY |
| Shower Pan | 7/3/2023 | Approved | BOBBY KEY |
| Insulation | 7/11/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 7/14/2023 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 7/14/2023 | Approved | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 4/25/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/23/2024 | Approved | BOBBY KEY |
| Final | 9/23/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 9/23/2024 | Approved | BOBBY KEY |
| HVAC-Final | 9/23/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 9/23/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/23/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 9/23/2024 | Approved | BOBBY KEY |
| Final | 9/30/2024 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 9/30/2024 | Approved | BOBBY KEY |