13001 W AETNA ST 91401
Certificate Information: 13001 W AETNA ST 91401
- Application / Permit
- 22014-20000-03225
- Plan Check / Job No.
- B22VN10020
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 40' X 29'-3" IRREGULAR SHAPED ADDITION TO THE REAR OF THE EXISTING SINGLE FAMILY DWELLING; CONVERT EXISTING GARAGE TO PART OF DWELLING; NEW 18'-9" X 19' ATTACHED GARAGE; ADD 4'-9" X 7' PORCH; 29'-9" X 20' IRREGULAR SHAPED ADDITION TO THE FRONT OF THE SFD
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | SELLA BENYAMIN |
| Corrections Issued | 7/19/2022 | SELLA BENYAMIN |
| Quality Review Completed | 7/25/2022 | STEVEN KIM |
| Building Plans Picked Up | 7/27/2022 | APPLICANT |
| Plan Check Approved | 8/23/2022 | SELLA BENYAMIN |
| Issued | 8/25/2022 | APPLICANT |
| CofO in Progress | 5/20/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 5/22/2024 | RUBEN SALAS |
| CofO Issued | 5/22/2024 | RUBEN SALAS |
| Permit Finaled | 5/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/21/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 8/4/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/4/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/8/2022 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 11/9/2022 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 11/9/2022 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 12/28/2022 | No Access for Inspection | JOHN COLEMAN |
| Underground Mechanical | 1/3/2023 | Approved | KIRK SANDERS |
| Insulation | 1/12/2023 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 4/11/2023 | Partial Approval | ROBERT GOLD |
| Rough-Elec/Plmb/HVAC | 5/3/2023 | Corrections Issued | KIRK SANDERS |
| Verify Sprinkler Sign Off | 5/3/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 5/9/2023 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 5/9/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 5/9/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/15/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 5/15/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 5/15/2023 | Approved | KIRK SANDERS |
| Insulation | 6/5/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 6/12/2023 | Approved | RAUL OLAGI |
| Shower Pan | 7/18/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 5/2/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 5/10/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 5/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 5/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 5/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 5/15/2024 | Approved | JOSE AVILA |
| HVAC-Final | 5/15/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 5/17/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 5/17/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 5/17/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 5/17/2024 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 5/20/2024 | Approved | OGANES TARAKHCHYAN |