638-638 1/2 E 85TH ST 90001

Certificate Information: 638-638 1/2 E 85TH ST 90001

Application / Permit
22014-20000-03210
Plan Check / Job No.
B22VN10004
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan CONVERT PORTION OF LOWER LEVEL (GARAGE AND (E) SFD) TO CREATE AN ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 3/18/2023
Issuing Office
Current Status
CofO Issued on 8/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 MICHAEL LOPEZ
Corrections Issued 8/5/2022 MICHAEL LOPEZ
Quality Review Completed 8/12/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 1/16/2023 MICHAEL LOPEZ
Plan Check Approved 2/28/2023 MICHAEL LOPEZ
Issued 3/18/2023 APPLICANT
CofO in Progress 8/1/2024 MICHAEL LEWIS
CofO Issued 8/5/2024 DEROLD HAUFF
Permit Finaled 8/5/2024 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 9/9/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/26/2022 STEVE MELGAR
Address approval Cleared 12/19/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/26/2023 Conditional Approval MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 5/30/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 5/30/2023 Approved MICHAEL LEWIS
Gas Test 6/9/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/9/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 6/20/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 6/20/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 6/26/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 6/26/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 7/18/2023 Approved MICHAEL LEWIS
Insulation 7/18/2023 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 7/21/2023 Approved MICHAEL LEWIS
Green Building Rough 7/21/2023 Approved MICHAEL LEWIS
Insulation 7/25/2023 No Access for Inspection DONALD CRICHLOW
Shower Pan 7/25/2023 No Access for Inspection DONALD CRICHLOW
Insulation 7/28/2023 Approved DONALD CRICHLOW
Shower Pan 7/28/2023 Approved DONALD CRICHLOW
Drywall Nailing 1/16/2024 Corrections Issued MICHAEL LEWIS
Service/Power Release 1/16/2024 Not Ready for Inspection MICHAEL LEWIS
Drywall Nailing 1/22/2024 Corrections Issued JOSE MACIAS
Drywall Nailing 1/31/2024 Approved MICHAEL LEWIS
Service/Power Release 4/3/2024 Not Ready for Inspection MICHAEL LEWIS
Final 5/2/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 5/2/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 5/2/2024 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 5/2/2024 Approved MICHAEL LEWIS
Final 7/31/2024 OK to Issue CofO MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV Approved MICHAEL LEWIS