631 W 58TH ST 90037
Certificate Information: 631 W 58TH ST 90037
- Application / Permit
- 22014-20000-03207
- Plan Check / Job No.
- B22VN10003
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan ADDITION TO AN EXISTING 1-STORY TYPE VB SFD. 1 OF 2.
- Permit Issued
- Issued on 2/9/2023
- Issuing Office
- Current Status
- CofO Issued on 4/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | QUAN NGHIEM |
| Corrections Issued | 8/11/2022 | QUAN NGHIEM |
| Quality Review Completed | 8/16/2022 | CHAD DOI |
| Applicant returned to address corrections | 8/24/2022 | QUAN NGHIEM |
| Applicant returned to address corrections | 11/29/2022 | QUAN NGHIEM |
| Plan Check Approved | 2/9/2023 | QUAN NGHIEM |
| Issued | 2/9/2023 | APPLICANT |
| CofO in Progress | 1/29/2024 | RONNIE MINDANAO |
| Permit Finaled | 4/5/2025 | DEROLD HAUFF |
| CofO Issued | 4/5/2025 | DEROLD HAUFF |
| Permit Finaled | 4/5/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 8/19/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 11/26/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 5/31/2023 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Partial Approval | STUART CHAPMAN |
| Wood Frame | 5/31/2023 | Partial Approval | STUART CHAPMAN |
| Insulation | 6/15/2023 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/15/2023 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 7/17/2023 | Approved | CHARLES BOGHOSKHAN |
| PLUMBING-Rough | 7/20/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/25/2023 | Approved | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 8/28/2023 | Approved | SABAS ALONSO |
| Final | 8/28/2023 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 8/28/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/28/2023 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 8/28/2023 | Approved | SABAS ALONSO |
| Final | 1/26/2024 | OK to Issue CofO | RONNIE MINDANAO |