2716 S PORTLAND ST 90007

Certificate Information: 2716 S PORTLAND ST 90007

Application / Permit
22014-20000-03201
Plan Check / Job No.
B22VN09991
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERTION OF (E) DETACHED CARPORT TO ACCESORY DWELLING UNIT WITH SECOND FLOOR ADDITION PER LAMC 12.22 A.33
Permit Issued
Issued on 4/13/2023
Issuing Office
Current Status
CofO Issued on 8/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/27/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 ARSALAN SHABESTARI
Corrections Issued 7/19/2022 ARSALAN SHABESTARI
Quality Review Completed 7/22/2022 GARO TELMI
Applicant returned to address corrections 10/12/2022 ARSALAN SHABESTARI
Plan Check Approved 4/12/2023 ARSALAN SHABESTARI
Issued 4/13/2023 APPLICANT
CofO in Progress 8/24/2023 SCOTT FINNILA
Permit Finaled 8/29/2023 DEROLD HAUFF
CofO Issued 8/29/2023 DEROLD HAUFF
Permit Finaled 8/29/2023 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 8/25/2022 JASON CHAN
Historic Resource Verification Cleared 8/26/2022 MAX LODER
Address approval Cleared 8/30/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/31/2022 STEVE MELGAR
Redevelopment Project Area Cleared 8/31/2022 DAVID URITA
Sewer availability Cleared 8/31/2022 STEVE MELGAR
Low Impact Development Cleared 3/29/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 4/4/2023 TREVOR QUAN

Contact Information

Architect Zbikowski,, Jeffrey; Lic. No.: NA35389       ,
Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 5/3/2023 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/3/2023 Corrections Issued BRENDAN MORELLI
HVAC-Rough 5/3/2023 Approved BRENDAN MORELLI
Shower Pan 5/3/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 5/9/2023 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 5/9/2023 Approved BRENDAN MORELLI
METHANE-Rough 5/9/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 5/9/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 5/10/2023 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 5/11/2023 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 5/11/2023 Approved BRENDAN MORELLI
Underground Mechanical 5/26/2023 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/2/2023 Approved BRENDAN MORELLI
Insulation 6/7/2023 Conditional Approval BRENDAN MORELLI
Drywall Nailing 6/12/2023 Partial Approval BRENDAN MORELLI
Drywall Nailing 6/14/2023 Approved BRENDAN MORELLI
Final 8/3/2023 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/3/2023 Approved ALEJANDRO DE ARTOLA
METHANE-Barrier 8/3/2023 Approved ALEJANDRO DE ARTOLA
METHANE-Subgrade 8/3/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/3/2023 SGSOV Not Required ALEJANDRO DE ARTOLA
Smoke Detectors 8/3/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/8/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Final 8/8/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 8/8/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/11/2023 Approved SCOTT FINNILA
Final 8/11/2023 Corrections Issued SCOTT FINNILA
Gas Test 8/11/2023 Approved SCOTT FINNILA
Green Building Final 8/11/2023 Approved SCOTT FINNILA
HVAC-Final 8/11/2023 Approved SCOTT FINNILA
PLUMBING-Final 8/11/2023 Approved SCOTT FINNILA
Pre-Inspection 8/11/2023 Partial Inspection SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 8/11/2023 SGSOV Approved SCOTT FINNILA
Service/Power Release 8/11/2023 Partial Inspection SCOTT FINNILA
Final 8/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/24/2023 OK to Issue CofO SCOTT FINNILA