322 E 60TH ST 90003
Certificate Information: 322 E 60TH ST 90003
- Application / Permit
- 22014-20000-03190
- Plan Check / Job No.
- B22VN09975
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert (E) Detached Garage + Addition to 1 ADU per LAMC 12.22 A.33 (c)-(d). [1,200 SQ FT TOTAL ADU]
- Permit Issued
- Issued on 12/27/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | HANS SANTIAGO |
| Corrections Issued | 7/8/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 12/1/2022 | HANS SANTIAGO |
| Plan Check Approved | 12/22/2022 | ANDREW SANTIAGO |
| Issued | 12/27/2022 | APPLICANT |
| CofO in Progress | 11/8/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 11/21/2023 | DEROLD HAUFF |
| CofO Issued | 11/21/2023 | DEROLD HAUFF |
| Permit Finaled | 11/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/30/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 12/2/2022 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 12/14/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 12/15/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 12/21/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Paniagua,, Cristobal; Lic. No.: C72894 | 1538 W 92ND ST LOS ANGELES, CA 90047 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/3/2023 | Corrections Issued | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 3/3/2023 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 3/3/2023 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 3/13/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/7/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2023 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 4/7/2023 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 4/7/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 6/5/2023 | Conditional Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 6/5/2023 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 6/5/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 6/9/2023 | Partial Approval | BRENDAN MORELLI |
| Insulation | 6/15/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 6/22/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 6/28/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 9/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 9/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 9/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 9/7/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/14/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 9/14/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Final | 9/14/2023 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Final | 9/14/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 9/14/2023 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 9/14/2023 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 9/14/2023 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 9/26/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/26/2023 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 9/26/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/8/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/8/2023 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |