14236 W HAYNES ST 91401

Certificate Information: 14236 W HAYNES ST 91401

Application / Permit
22014-20000-03189
Plan Check / Job No.
B22VN09973
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND STORAGE TO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 7/1/2024
Issuing Office
Current Status
CofO Issued on 1/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2022 APPLICANT
Assigned to Plan Check Engineer 7/6/2022 SELLA BENYAMIN
Corrections Issued 7/6/2022 SELLA BENYAMIN
Plan Check Approved 6/8/2024 GIOVANNY CHAVEZ
Issued 7/1/2024 APPLICANT
CofO in Progress 12/30/2024 RYAN SALAZAR
Permit Finaled 1/7/2025 RUBEN SALAS
CofO Issued 1/7/2025 RUBEN SALAS
Permit Finaled 1/7/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/7/2022 CARLOS AGUILERA
Sewer availability Cleared 7/7/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/15/2022 CARLOS AGUILERA
HPOZ Cleared 5/1/2024 NATHALY DE LA PAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/23/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 9/10/2024 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 9/10/2024 Approved MICHEL ABAJAN
Green Building Rough 9/10/2024 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 9/10/2024 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 9/10/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 9/19/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 9/19/2024 Corrections Issued JENNIFER RABUCHIN
Sewer 9/19/2024 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 9/19/2024 Partial Approval JENNIFER RABUCHIN
Wood Frame 9/19/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 9/30/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/30/2024 Approved RYAN SALAZAR
Sewer 9/30/2024 Approved RYAN SALAZAR
Shower Pan 9/30/2024 Approved RYAN SALAZAR
Insulation 10/8/2024 Approved RYAN SALAZAR
Drywall Nailing 10/17/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 12/27/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 12/27/2024 Approved RYAN SALAZAR
Final 12/27/2024 OK to Issue CofO RYAN SALAZAR
Gas Test 12/27/2024 Approved RYAN SALAZAR
Green Building Final 12/27/2024 Approved RYAN SALAZAR
Green Building Rough 12/27/2024 Approved RYAN SALAZAR
HVAC-Final 12/27/2024 Approved RYAN SALAZAR
PLUMBING-Final 12/27/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/27/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 12/27/2024 Approved RYAN SALAZAR
Smoke Detectors 12/27/2024 Approved RYAN SALAZAR