16848 W NANETTE ST 91344

Certificate Information: 16848 W NANETTE ST 91344

Application / Permit
22014-20000-03172
Plan Check / Job No.
B22VN09875
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 52'-9" X 78'-8" IRREGULAR SHAPED 2-STORY ADDITION AND MAJOR REMODEL TO (E) 2-STORY SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/18/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 RAPHAEL ROSAS
Corrections Issued 8/4/2022 RAPHAEL ROSAS
Quality Review Completed 8/12/2022 STEVEN KIM
Building Plans Picked Up 8/15/2022 APPLICANT
Applicant returned to address corrections 9/13/2022 RAPHAEL ROSAS
Plan Check Approved 10/18/2022 RAPHAEL ROSAS
Issued 10/18/2022 APPLICANT
CofO in Progress 10/24/2023 JAVIER RAMOS JR
Permit Finaled 12/29/2023 RUBEN SALAS
CofO Issued 12/29/2023 RUBEN SALAS
Permit Finaled 12/29/2023 RUBEN SALAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/4/2022 MEGAN GODINEZ
BHO/Hillside ordinance Cleared 8/4/2022 MEGAN GODINEZ
BHO/Hillside ordinance Cleared 8/4/2022 MEGAN GODINEZ
BHO/Hillside ordinance Cleared 8/4/2022 MEGAN GODINEZ
BHO/Hillside ordinance Cleared 8/4/2022 MEGAN GODINEZ
Sewer availability Cleared 8/4/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/5/2022 MEGAN GODINEZ
Distance to fire station Cleared 8/30/2022 MATTHEW CRAIG
Low Impact Development Cleared 9/29/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 9/30/2022 MEGAN GODINEZ
GPI Written Notices Cleared 10/18/2022 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 10/18/2022 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 21520 BURBANK BLVD APT 219      WOODLAND HILLS, CA 91367

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/30/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 12/6/2022 Partial Approval JAVIER RAMOS JR
Sewer 12/6/2022 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 12/14/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Not Ready for Inspection JAVIER RAMOS JR
Structural Steel Frame 1/26/2023 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Partial Approval JENNIFER RABUCHIN
Structural Steel Frame 1/31/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Not Ready for Inspection JAVIER RAMOS JR
Deputy Wood Construction 3/29/2023 Conditional Approval MICHAEL SMITH
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 4/17/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/17/2023 Partial Approval JAVIER RAMOS JR
Green Building Rough 4/17/2023 Approved JAVIER RAMOS JR
HVAC-Rough 4/17/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 4/17/2023 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 4/17/2023 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 4/27/2023 Not Ready for Inspection JAVIER RAMOS JR
Verify Sprinkler Sign Off 4/27/2023 Approved JAVIER RAMOS JR
Insulation 5/3/2023 Partial Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 5/23/2023 Approved JAVIER RAMOS JR
Drywall Nailing 5/23/2023 Approved JAVIER RAMOS JR
Insulation 5/23/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/23/2023 Approved JAVIER RAMOS JR
Shower Pan 5/23/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/24/2023 Corrections Issued JAVIER RAMOS JR
Service/Power Release 5/26/2023 Approved JAVIER RAMOS JR
Underground Mechanical 5/26/2023 Partial Approval JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/21/2023 SGSOV Not Ready JAVIER RAMOS JR
BUILDING-Rough-Frame 9/27/2023 Approved JAVIER RAMOS JR
Final 9/27/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 9/27/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/27/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 9/27/2023 Approved JAVIER RAMOS JR
Final 10/16/2023 OK to Issue CofO JAVIER RAMOS JR