8943 N BALBOA BLVD 91325

Certificate Information: 8943 N BALBOA BLVD 91325

Application / Permit
22014-20000-03154
Plan Check / Job No.
B22VN09810
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
3' X 24' ADDITION AND CONVERT (E) DETACHED GARAGE W/ WORKSHOP INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). DEMO 3'X24' NORTH SIDE POR OF THE GARAGE. ALL WORK PER WFPP.
Permit Issued
Issued on 9/23/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 HAYATO TSUCHIYA
Corrections Issued 6/25/2022 HAYATO TSUCHIYA
Building Plans Picked Up 6/28/2022 APPLICANT
Plan Check Approved 9/20/2022 SERGIO MUNIZ
Plan Check Approved 9/20/2022 SERGIO MUNIZ
Issued 9/23/2022 APPLICANT
CofO in Progress 10/6/2023 JAVIER RAMOS JR
CofO Issued 12/19/2023 RUBEN SALAS
Permit Finaled 12/19/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/30/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/30/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/5/2022 CARLOS AGUILERA
Sewer availability Cleared 7/5/2022 CARLOS AGUILERA
Construction near power lines Cleared 9/4/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/7/2022 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 10/11/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 10/11/2022 Partial Approval JAVIER RAMOS JR
Sewer 10/11/2022 Approved JAVIER RAMOS JR
Underground Mechanical 10/11/2022 Partial Approval JAVIER RAMOS JR
Underground Mechanical 10/13/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 11/17/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 11/17/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Approved JAVIER RAMOS JR
Green Building Rough 11/17/2022 Approved JAVIER RAMOS JR
HVAC-Rough 11/17/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 11/17/2022 Approved JAVIER RAMOS JR
Insulation 12/12/2022 Approved RYAN SALAZAR
BUILDING-Rough-Frame 12/23/2022 Approved JAVIER RAMOS JR
Drywall Nailing 12/23/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/23/2022 Approved JAVIER RAMOS JR
Shower Pan 12/23/2022 Approved JAVIER RAMOS JR
Final 9/21/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 9/21/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/21/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 9/21/2023 Approved JAVIER RAMOS JR
Final 9/28/2023 OK to Issue CofO JAVIER RAMOS JR