9336-9340 N RHEA AVE 91324
Certificate Information: 9336-9340 N RHEA AVE 91324
- Application / Permit
- 22014-20000-03152
- Plan Check / Job No.
- B22VN09792
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE (349 SQFT) AND PORTION OF SINGLE FAMILY DWELLING (181 SQFT) INTO ADU (530 SQFT) PER GCS65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Current Status
- CofO Issued on 8/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | TROY DEGUZMAN |
| Corrections Issued | 7/29/2022 | TROY DEGUZMAN |
| Quality Review Completed | 8/15/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 8/17/2022 | APPLICANT |
| Plan Check Approved | 9/13/2022 | PETER MOSESIAN |
| Issued | 12/16/2022 | APPLICANT |
| CofO in Progress | 8/21/2023 | JOHN KIDWELL |
| Permit Finaled | 8/24/2023 | JOHN JANSON |
| CofO Issued | 8/24/2023 | JOHN JANSON |
| Permit Finaled | 8/24/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/3/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 8/24/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/26/2022 | COLIN LOREDO |
| Green Code | Cleared | 9/8/2022 | TROY DEGUZMAN |
| Miscellaneous | Cleared | 9/8/2022 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/26/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 2/6/2023 | Conditional Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 2/9/2023 | Approved | MORRIS JACKSON |
| Special/Order Compliance | 2/9/2023 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 2/22/2023 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 2/22/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 2/24/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 2/24/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Rough | 2/24/2023 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 3/2/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 3/6/2023 | Not Ready for Inspection | PETER FOLLING |
| Green Building Rough | 3/6/2023 | Approved | PETER FOLLING |
| Drywall Nailing | 3/10/2023 | Approved | DAVID SCANTLIN |
| Insulation | 3/10/2023 | Approved | DAVID SCANTLIN |
| Final | 3/21/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 3/21/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Interior/Exterior Lathing | 3/21/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/21/2023 | SGSOV Not Ready | DAVID SCANTLIN |
| Pre-Inspection | 3/28/2023 | Approved | DAVID SCANTLIN |
| Final | 4/21/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 4/21/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 4/21/2023 | Approved | DAVID SCANTLIN |
| Final | 5/1/2023 | Corrections Issued | JOHN KIDWELL |
| Final | 8/21/2023 | OK to Issue CofO | JOHN KIDWELL |