21820 W MICHALE ST 91304

Certificate Information: 21820 W MICHALE ST 91304

Application / Permit
22014-20000-03115
Plan Check / Job No.
B22VN09739
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 28'-7" X 20'-11" LIVING ROOM / DINING ROOM AND 23'-1" X 16'-4" BEDROOM TO SINGLE FAMILY DWELLING - ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/7/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 DANIEL ABRAMYAN
Corrections Issued 6/25/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 7/11/2022 DANIEL ABRAMYAN
Building Plans Picked Up 7/12/2022 APPLICANT
Applicant returned to address corrections 8/18/2022 OMAR GARNICA
Plan Check Approved 9/2/2022 ANGELICA MARTINEZ
Issued 9/7/2022 APPLICANT
CofO in Progress 3/4/2024 CHRIS CHRISTENSEN
CofO in Progress 5/24/2024 HORACE FULTZ
Permit Finaled 1/15/2025 JOHN JANSON
CofO Issued 1/15/2025 JOHN JANSON
Permit Finaled 1/15/2025 JOHN JANSON

Permit Application Clearance Information

Sewer availability Cleared 7/25/2022 MEGAN GODINEZ
Low Impact Development Cleared 8/29/2022 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 8/30/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 8/30/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 8/30/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 8/30/2022 MEGAN GODINEZ

Contact Information

Contractor Supreme Remodeling Inc; Lic. No.: 939981-B 14545 VICTORY BLVD UNIT 401      VAN NUYS, CA 91411
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/27/2022 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 12/27/2022 Not Ready for Inspection KRISTEN CAUSEY
Footing/Foundation/Slab 12/27/2022 Not Ready for Inspection KRISTEN CAUSEY
Excavation/Setback/Form/Re-Bar 12/29/2022 Approved KRISTEN CAUSEY
Deputy Other (see comments) 3/28/2023 Conditional Approval MORRIS JACKSON
Deputy Wood Construction 3/28/2023 Conditional Approval CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 3/29/2023 Approved HORACE FULTZ
Wood Frame 3/29/2023 Approved HORACE FULTZ
Interior/Exterior Lathing 4/12/2023 Partial Approval HORACE FULTZ
Pre-Inspection 4/12/2023 Partial Inspection JUSTIN HAWLEY
Insulation 4/28/2023 Approved JUSTIN HAWLEY
Drywall Nailing 5/4/2023 Approved DAVID SCANTLIN
Shower Pan 6/5/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/12/2023 Approved MORRIS JACKSON
BUILDING-Rough-Frame 11/15/2023 Approved CHRIS CHRISTENSEN
Final 11/15/2023 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 11/15/2023 Approved CHRIS CHRISTENSEN
Green Building Final 11/15/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 11/15/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 11/15/2023 Approved CHRIS CHRISTENSEN
Green Building Final 1/4/2024 Approved CHRIS CHRISTENSEN
Final 3/1/2024 OK to Issue CofO CHRIS CHRISTENSEN
Special/Order Compliance 5/29/2024 Corrections Issued JEFFREY HARTLINE