12366 W EVENSONG DR 90064

Certificate Information: 12366 W EVENSONG DR 90064

Application / Permit
22014-20000-03100
Plan Check / Job No.
B22VN09713
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) PORCH TO SFD (107 SQFT), W/ NEW (13'-0"x3'-8"), 14.5 SQFT PORCH W/ INTERIOR REMODEL TO (E) SFD 2ND FLOOR AND ENCLOSE (E) LAUNDRY ROOM TO NEW BEDROOMS.
Permit Issued
Issued on 9/6/2022
Issuing Office
Current Status
Issued on 9/6/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/22/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 PETER MOSESIAN
Corrections Issued 7/28/2022 PETER MOSESIAN
Quality Review Completed 8/4/2022 OMID HEDAYAT
Building Plans Picked Up 8/5/2022 APPLICANT
Applicant returned to address corrections 8/25/2022 PETER MOSESIAN
Plan Check Approved 8/30/2022 PETER MOSESIAN
Issued 9/6/2022 APPLICANT
CofO in Progress 5/25/2023 JOHNNY MIRANDA
CofO Issued-Status Void 6/8/2023 DANIEL ORRANTE
Permit Finaled-Status Void 6/8/2023 DANIEL ORRANTE
Re-Activate Permit 8/23/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/3/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 8/11/2022 CATHERINE ADROVER

Contact Information

Contractor Voss Construction And Development Inc; Lic. No.: 886103-B 4500 PARK GRANADA BLVD STE 202      CALABASAS, CA 91302
Engineer Sayah,, Daniel H; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/21/2022 Conditional Approval JOHN KIDWELL
PLUMBING-Rough 9/21/2022 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Partial Approval CLAYTON GRAHAM
Green Building Rough 10/14/2022 Not Ready for Inspection CLAYTON GRAHAM
BUILDING-Rough-Frame 11/2/2022 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 11/2/2022 Corrections Issued JOHNNY MIRANDA
Green Building Rough 11/2/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 11/2/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 11/2/2022 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 11/4/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 11/4/2022 Approved JOHNNY MIRANDA
Green Building Rough 11/4/2022 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 11/4/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 11/16/2022 Partial Approval JOHNNY MIRANDA
Shower Pan 11/16/2022 Approved JOHNNY MIRANDA
Insulation 11/18/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 11/18/2022 Approved JOHNNY MIRANDA
Drywall Nailing 11/29/2022 Conditional Approval ASHLEY THOMPSON
Final 11/29/2022 Corrections Issued ASHLEY THOMPSON
Green Building Rough 11/29/2022 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 5/8/2023 Approved JOHNNY MIRANDA
Drywall Nailing 5/8/2023 Approved JOHNNY MIRANDA
Final 5/8/2023 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 5/8/2023 Approved JOHNNY MIRANDA
Green Building Final 5/8/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 5/8/2023 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 5/8/2023 Approved JOHNNY MIRANDA
Final 5/24/2023 OK to Issue CofO JOHNNY MIRANDA