17277 W LASSEN ST 91325
Certificate Information: 17277 W LASSEN ST 91325
- Application / Permit
- 22014-20000-03092
- Plan Check / Job No.
- B22VN09674
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 642 SF ADDITION TO AND CONVERT THE (E) 407 SF GARAGE INTO A (N) 1049 SF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d), AND RE-FRAME ENTIRE BUILDING PER ENGINEERING
- Permit Issued
- Issued on 2/15/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 7/2/2022 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 7/6/2022 | APPLICANT |
| Applicant returned to address corrections | 11/7/2022 | HAYATO TSUCHIYA |
| Plan Check Approved | 12/16/2022 | ISIS ARGUETA |
| Plan Check Approved | 12/16/2022 | RAMA DABADGE |
| Issued | 2/15/2023 | APPLICANT |
| CofO in Progress | 8/23/2023 | JAVIER RAMOS JR |
| Permit Finaled | 10/3/2023 | RUBEN SALAS |
| CofO Issued | 10/3/2023 | RUBEN SALAS |
| Permit Finaled | 10/3/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/11/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 8/19/2022 | MEGAN GODINEZ |
| Low Impact Development | Cleared | 10/25/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 11/3/2022 | MEGAN GODINEZ |
| Grading Pre-Inspection | Cleared | 11/7/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Dwell Catalyst; Lic. No.: 1021730-B | 9629 GERALD AVE NORTHRIDGE, CA 91343 |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1929 GREENLEAF DR WEST COVINA, CA 91792 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/23/2023 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 3/17/2023 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 3/17/2023 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 3/23/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 3/23/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/24/2023 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/24/2023 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 4/24/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 4/24/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/24/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/2/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/2/2023 | Partial Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/2/2023 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 5/2/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/10/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 5/10/2023 | Corrections Issued | JAVIER RAMOS JR |
| Drywall Nailing | 5/18/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/18/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 5/18/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/7/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/7/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/20/2023 | Approved | JAVIER RAMOS JR |
| Final | 7/20/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 7/20/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 7/20/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 7/20/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/20/2023 | SGSOV Not Ready | JAVIER RAMOS JR |
| Smoke Detectors | 7/20/2023 | Approved | JAVIER RAMOS JR |
| Final | 7/28/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Not Ready | JAVIER RAMOS JR |
| Final | 8/4/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/4/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Final | 8/22/2023 | OK to Issue CofO | JAVIER RAMOS JR |