7699 N WHITSETT AVE 91605
Certificate Information: 7699 N WHITSETT AVE 91605
- Application / Permit
- 22014-20000-03091
- Plan Check / Job No.
- B22VN09672
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE (E) 323 SF DET. GARAGE EXCEPT 5 LINEAR FEET OF WALL AND FOUNDATION. REBUILD 20' X 27'-4" 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) W/ 9'-4" X 20' STORAGE. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | RAPHAEL ROSAS |
| Corrections Issued | 7/11/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 7/14/2022 | STEVEN KIM |
| Building Plans Picked Up | 7/21/2022 | APPLICANT |
| Applicant returned to address corrections | 9/9/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 9/12/2022 | RAPHAEL ROSAS |
| Issued | 9/12/2022 | APPLICANT |
| CofO in Progress | 10/13/2023 | CHRISTOPHER ROJAS |
| Permit Finaled | 1/24/2024 | RUBEN SALAS |
| CofO Issued | 1/24/2024 | RUBEN SALAS |
| Permit Finaled | 1/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/25/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 7/27/2022 | MEGAN GODINEZ |
| Low Impact Development | Cleared | 7/28/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 8/4/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/31/2023 | Partial Approval | MATTHEW NELSON |
| Sewer | 1/31/2023 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/7/2023 | Approved | MATTHEW NELSON |
| METHANE-Barrier | 2/7/2023 | Approved | MATTHEW NELSON |
| METHANE-Subgrade | 2/7/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/21/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 2/21/2023 | Not Ready for Inspection | MATTHEW NELSON |
| MERV13>=Rough | 2/21/2023 | Not Ready for Inspection | MATTHEW NELSON |
| METHANE-Rough | 2/21/2023 | Approved | MATTHEW NELSON |
| Wood Frame | 2/21/2023 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/8/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 3/8/2023 | Not Ready for Inspection | MATTHEW NELSON |
| MERV13>=Rough | 3/8/2023 | Approved | MATTHEW NELSON |
| Wood Frame | 3/8/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/21/2023 | Approved | MATTHEW NELSON |
| Gas Test | 4/21/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 4/21/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 4/21/2023 | Approved | MATTHEW NELSON |
| Sewer | 4/21/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/24/2023 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/24/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/24/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 5/9/2023 | Approved | MATTHEW NELSON |
| Insulation | 5/9/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/9/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 5/19/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 8/8/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 8/8/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 8/8/2023 | Approved | MATTHEW NELSON |
| HVAC-Final | 8/8/2023 | Approved | MATTHEW NELSON |
| MERV13>=Final | 8/8/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 8/8/2023 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/8/2023 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 8/8/2023 | Approved | MATTHEW NELSON |
| Final | 8/11/2023 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Approved | MATTHEW NELSON |
| Final | 10/12/2023 | OK to Issue CofO | CHRISTOPHER ROJAS |