3568 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3568 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 22014-20000-03085
- Plan Check / Job No.
- B22VN09650
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 23'-11" X 7'-5" ONE STORY ADDITION AND 19'-1" X 3'-4' SECOND STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 4/25/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | SELLA BENYAMIN |
| Corrections Issued | 7/25/2022 | SELLA BENYAMIN |
| Quality Review Completed | 7/29/2022 | STEVEN KIM |
| Building Plans Picked Up | 8/2/2022 | APPLICANT |
| Plan Check Approved | 9/1/2022 | SELLA BENYAMIN |
| Issued | 4/25/2024 | APPLICANT |
| CofO in Progress | 10/30/2024 | DANIEL VERA |
| Permit Finaled | 11/5/2024 | RICHARD STEINBACH |
| CofO Issued | 11/5/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/5/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/10/2022 | ANA VILLA |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | ANA VILLA |
Contact Information
| Contractor | Green Oak Builders; Lic. No.: 929471-B | 5310 NORTON STREET TORRANCE, CA 90503 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/29/2024 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 5/9/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 5/17/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 7/23/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 7/23/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 7/30/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 7/30/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 7/30/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 8/5/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 8/5/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 8/5/2024 | Partial Approval | JESUS PINEDA |
| Insulation | 8/7/2024 | Approved | JESUS PINEDA |
| Shower Pan | 8/7/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 8/13/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/13/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 10/24/2024 | Approved | DANIEL VERA |
| Final | 10/24/2024 | Corrections Issued | DANIEL VERA |
| Green Building Final | 10/24/2024 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 10/24/2024 | Approved | DANIEL VERA |
| PLUMBING-Final | 10/24/2024 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 10/24/2024 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 10/24/2024 | Approved | DANIEL VERA |
| Final | 10/29/2024 | OK to Issue CofO | DANIEL VERA |
| Green Building Final | 10/29/2024 | Approved | DANIEL VERA |