12422-12424 W GAGER ST 91331
Certificate Information: 12422-12424 W GAGER ST 91331
- Application / Permit
- 22014-20000-03062
- Plan Check / Job No.
- B22VN09587
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- [CUGU - SUBJECT USE] *EPLAN* CONVERT PORTION OF (E) 1-STORY SFD WITH ATTACHED 2-CAR GARAGE TO ADU (713 SF) PER CA GC 65852.2(e)(1)(A). - EXISTING TWO BEDROOMS, BATH, LIVING ROOM - NEW KITCHEN
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Current Status
- CofO Issued on 1/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2022 | VIVIAN LAO |
| Corrections Issued | 7/11/2022 | VIVIAN LAO |
| Plan Check Approved | 7/20/2022 | VIVIAN LAO |
| Issued | 7/22/2022 | APPLICANT |
| CofO in Progress | 1/10/2023 | MICHEL ABAJAN |
| Permit Finaled | 1/12/2023 | MICHAEL SMITH |
| CofO Issued | 1/12/2023 | MICHAEL SMITH |
| Permit Finaled | 1/12/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2022 | DAGOVERTO GUERRERO |
| Clean Up Green Up | Cleared | 7/13/2022 | ASHLEY RODARTE |
| Sewer availability | Cleared | 7/13/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2022 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 7/15/2022 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/12/2022 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 8/19/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Gas Test | 9/16/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| PLUMBING-Rough | 9/16/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 9/23/2022 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 9/28/2022 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/24/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 11/10/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/10/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/10/2023 | Approved | MICHEL ABAJAN |
| Final | 1/10/2023 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 1/10/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 1/10/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 1/10/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/10/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/10/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 1/10/2023 | Approved | MICHEL ABAJAN |