5847 N SHIRLEY AVE 91356
Certificate Information: 5847 N SHIRLEY AVE 91356
- Application / Permit
- 22014-20000-03051
- Plan Check / Job No.
- B22VN09545
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Addition to the (E) House
- Permit Issued
- Issued on 1/13/2023
- Issuing Office
- Current Status
- CofO in Progress on 1/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | JAD BASMA |
| Corrections Issued | 7/10/2022 | JAD BASMA |
| Quality Review Completed | 7/19/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 12/16/2022 | JAD BASMA |
| Plan Check Approved | 1/4/2023 | JAD BASMA |
| Issued | 1/13/2023 | APPLICANT |
| CofO in Progress | 12/16/2024 | JON MCHUGH |
| CofO in Progress | 12/31/2024 | SEAN WIRCH |
| No Progress | 1/10/2025 | SEAN WIRCH |
| CofO in Progress | 1/10/2025 | SEAN WIRCH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 8/11/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 11/21/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 11/22/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/17/2023 | Conditional Approval | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 4/19/2023 | Approved | JON MCHUGH |
| Deputy Reinf. Concrete | 4/20/2023 | Approved | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 4/24/2023 | Not Ready for Inspection | JON MCHUGH |
| Underground Mechanical | 4/24/2023 | Not Ready for Inspection | JON MCHUGH |
| Deputy Drilled-In Anchors | 5/2/2023 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 5/8/2023 | Approved | JON MCHUGH |
| Underground Mechanical | 5/8/2023 | Partial Approval | JON MCHUGH |
| Deputy Drilled-In Anchors | 5/11/2023 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Rough | 7/28/2023 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 7/28/2023 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Approved | JON MCHUGH |
| HVAC-Rough | 8/3/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 9/15/2023 | Conditional Approval | JON MCHUGH |
| Interior/Exterior Lathing | 9/15/2023 | Partial Approval | JON MCHUGH |
| Shower Pan | 9/15/2023 | Approved | JON MCHUGH |
| Insulation | 10/2/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 10/27/2023 | Approved | JON MCHUGH |
| Drywall Nailing | 10/27/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 12/13/2023 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Final | 6/25/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 6/25/2024 | Not Ready for Inspection | JON MCHUGH |
| Final | 11/12/2024 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 11/12/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 11/12/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 11/26/2024 | Approved | JON MCHUGH |
| Final | 11/26/2024 | Partial Approval | JON MCHUGH |
| HVAC-Final | 11/26/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 11/26/2024 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 11/26/2024 | Approved | JON MCHUGH |
| Final | 12/16/2024 | OK to Issue CofO | JON MCHUGH |