22741 W ANGEL LANE 91304

Certificate Information: 22741 W ANGEL LANE 91304

Application / Permit
22014-20000-03046
Plan Check / Job No.
B22VN09543
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF A (N) 15'-9" X 16' COVERED PATIO WITH A 18'-3" x16' DECK ACCESSIBLE FROM 2ND FLOOR . - patio/deck shall be sprinklered thru-out
Permit Issued
Issued on 9/15/2022
Issuing Office
Valley
Current Status
CofO Issued on 6/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2022 APPLICANT
Assigned to Plan Check Engineer 6/21/2022 LUIS RINCON
Corrections Issued 6/21/2022 LUIS RINCON
Building Plans Picked Up 7/7/2022 APPLICANT
Applicant returned to address corrections 9/14/2022 LUISANGEL VALENZUELA
Plan Check Approved 9/15/2022 ALEC MOUSAKHANIAN
Issued 9/15/2022 APPLICANT
CofO in Progress 3/22/2023 CHRIS CHRISTENSEN
Permit Finaled 6/22/2023 JOHN JANSON
CofO Issued 6/22/2023 JOHN JANSON
Permit Finaled 6/22/2023 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/26/2022 CARLOS AGUILERA
"Q" conditions Cleared 7/28/2022 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 8/10/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Wilson,, Kalen; Lic. No.: C83753 25 AMADOR WAY      ALISO VIEJO, CA 92656

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/30/2022 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 10/11/2022 Approved CHRIS CHRISTENSEN
Deputy Reinf. Concrete 10/18/2022 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/9/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/9/2022 Partial Approval CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 11/9/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 11/23/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/14/2022 Approved CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 12/14/2022 Corrections Issued CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 12/14/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 1/10/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 1/10/2023 Partial Approval CHRIS CHRISTENSEN
Final 3/3/2023 Not Ready for Inspection KRISTEN CAUSEY
Footing/Foundation/Slab 3/3/2023 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 3/3/2023 SGSOV Approved KRISTEN CAUSEY
Smoke Detectors 3/3/2023 Approved KRISTEN CAUSEY
Final 3/6/2023 OK to Issue CofO CHRIS CHRISTENSEN