6817 N YOLANDA AVE 91335
Certificate Information: 6817 N YOLANDA AVE 91335
- Application / Permit
- 22014-20000-03031
- Plan Check / Job No.
- B22VN09505
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE 6" X 18' PORTION OF DETACHED GARAGE AND CONVERT REMAINING 18' X 19'-6" AND ADD 20'-9" X 24'-10" IREGGULAR SHAPED 2ND STORY TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/20/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | RAPHAEL ROSAS |
| Corrections Issued | 7/5/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 7/14/2022 | STEVEN KIM |
| Building Plans Picked Up | 7/15/2022 | APPLICANT |
| Plan Check Approved | 9/1/2022 | RAPHAEL ROSAS |
| Issued | 9/20/2022 | APPLICANT |
| CofO in Progress | 1/3/2024 | JEFFREY BULL |
| CofO Issued | 2/9/2024 | JOHN JANSON |
| Permit Finaled | 2/9/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2022 | MEGAN GODINEZ |
| Certificate of Compliance | Cleared | 7/19/2022 | NATHAN ROMINE |
| Roof/Waste drainage to street | Cleared | 7/19/2022 | MEGAN GODINEZ |
| ZI | Cleared | 7/19/2022 | NATHAN ROMINE |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 8/3/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 8/3/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 8/3/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 8/3/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Van, Valkenburg, John; Lic. No.: C74939 | 13259 KISMET AVE SYLMAR, CA 91342 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/23/2023 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 3/7/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Partial Approval | JEFFREY BULL |
| Drywall Nailing | 4/19/2023 | Not Ready for Inspection | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 4/19/2023 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 6/22/2023 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 6/22/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 7/5/2023 | Approved | SEAN WIRCH |
| Green Building Rough | 7/5/2023 | Not Ready for Inspection | SEAN WIRCH |
| Interior/Exterior Lathing | 7/5/2023 | Partial Approval | SEAN WIRCH |
| BUILDING-Rough-Frame | 7/19/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 7/19/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 7/19/2023 | Approved | JEFFREY BULL |
| Insulation | 7/24/2023 | Corrections Issued | JUSTIN HAWLEY |
| Insulation | 7/28/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 8/11/2023 | Approved | JEFFREY BULL |
| Shower Pan | 8/11/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 8/15/2023 | Approved | JEFFREY BULL |
| Final | 11/29/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 11/29/2023 | Not Ready for Inspection | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 11/29/2023 | Not Ready for Inspection | JEFFREY BULL |
| Final | 1/2/2024 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 1/2/2024 | Approved | JEFFREY BULL |
| Smoke Detectors | 1/2/2024 | Approved | JEFFREY BULL |