7508 S WHITLOCK AVE 90293
Certificate Information: 7508 S WHITLOCK AVE 90293
- Application / Permit
- 22014-20000-03025
- Plan Check / Job No.
- B22VN09490
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE- 27'-3"X32' (N) SECOND STORY ADDITION WITH OPEN ROOF DECK ABOVE OVER (E) SFD WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 4/5/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | DAWN MC NULTY |
| Corrections Issued | 8/2/2022 | DAWN MC NULTY |
| Quality Review Completed | 8/8/2022 | STEVEN KIM |
| Building Plans Picked Up | 8/10/2022 | APPLICANT |
| Applicant returned to address corrections | 10/5/2023 | DAWN MC NULTY |
| Applicant returned to address corrections | 1/10/2024 | DAWN MC NULTY |
| Plan Check Approved | 2/7/2024 | DAWN MC NULTY |
| Issued | 4/5/2024 | APPLICANT |
| Re-Activate Permit | 2/5/2025 | TEMISTOCLES CAAL |
| Permit Expired-Status Void | 2/5/2025 | TEMISTOCLES CAAL |
| CofO in Progress | 2/5/2025 | MICHAEL PELHAM |
| CofO Issued | 2/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| CPC | Cleared | 11/18/2022 | DANIEL CORONADO |
| CPC | Cleared | 11/18/2022 | DANIEL CORONADO |
| Address approval | Cleared | 7/28/2023 | JASON NG |
| Sewer availability | Cleared | 7/28/2023 | JASON NG |
| Permit | Cleared | 7/31/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2023 | JASON NG |
| Grading Pre-Inspection | Cleared | 8/3/2023 | SERGIO VALENZUELA |
| Coastal Zone | Cleared | 11/2/2023 | MAYELA VILLA |
| Miscellaneous | Cleared | 11/2/2023 | MAYELA VILLA |
| Low Impact Development | Cleared | 1/24/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/24/2024 | ANDREA SAINT-ANTONIN |
| GPI Written Notices | Cleared | 2/7/2024 | DAWN MC NULTY |
Contact Information
| Architect | Ginter,, Gregory Hopkins; Lic. No.: C30686 | 1525 PEARL STREET SANTA MONICA, CA 90405 |
| Contractor | Adar Builders Inc; Lic. No.: 1051859-B | 7673 WINNETKA AVENUE WINNETKA, CA 91306 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/13/2024 | Approved | BOBBY KEY |
| Deputy Reinf. Concrete | 5/31/2024 | Conditional Approval | BOBBY KEY |
| Deputy Steel/Welding | 6/3/2024 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Partial Approval | BOBBY KEY |
| Deputy Wood Construction | 8/14/2024 | No Access for Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 8/19/2024 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 8/19/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 8/19/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 8/19/2024 | Approved | BOBBY KEY |
| Deputy Steel/Welding | 9/3/2024 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 9/11/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 9/11/2024 | Approved | BOBBY KEY |
| Insulation | 9/11/2024 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 9/11/2024 | Not Ready for Inspection | BOBBY KEY |
| Service/Power Release | 9/11/2024 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 10/7/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 10/7/2024 | Approved | BOBBY KEY |
| Green Building Rough | 10/7/2024 | Approved | BOBBY KEY |
| Insulation | 10/7/2024 | Not Ready for Inspection | BOBBY KEY |
| Service/Power Release | 10/7/2024 | Approved | BOBBY KEY |
| Deputy Wood Construction | 10/11/2024 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 10/17/2024 | Approved | BOBBY KEY |
| Insulation | 10/17/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 10/28/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 10/28/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 10/31/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 1/6/2025 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 1/6/2025 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 1/6/2025 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 1/6/2025 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 1/6/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/27/2025 | Approved | BOBBY KEY |
| Final | 1/27/2025 | Corrections Issued | BOBBY KEY |
| Green Building Final | 1/27/2025 | Approved | BOBBY KEY |
| HVAC-Final | 1/27/2025 | Approved | BOBBY KEY |
| Structural Steel Frame | 1/27/2025 | Approved | BOBBY KEY |
| Final | 2/4/2025 | OK to Issue CofO | TEMISTOCLES CAAL |