6653-6655 N QUARTZ AVE 91306
Certificate Information: 6653-6655 N QUARTZ AVE 91306
- Application / Permit
- 22014-20000-03023
- Plan Check / Job No.
- B22VN09485
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 20'-0" X 19'-6" ADDITION TO AND CONVERT THE (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). WORK PER WFPP AND ENGINEER DETAIL.
- Permit Issued
- Issued on 6/23/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 6/30/2022 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 3/8/2023 | ISIS ARGUETA |
| Plan Check Approved | 6/13/2023 | ALEC MOUSAKHANIAN |
| Issued | 6/23/2023 | APPLICANT |
| CofO in Progress | 3/13/2024 | ALEXANDER HANDY |
| Permit Finaled | 8/7/2024 | JOHN JANSON |
| CofO Issued | 8/7/2024 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 1/18/2023 | STEVEN WECHSLER |
| Address approval | Cleared | 1/19/2023 | RYAN KIM |
| Roof/Waste drainage to street | Cleared | 1/19/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2023 | RYAN KIM |
| Sewer availability | Cleared | 1/26/2023 | RYAN KIM |
| Construction near power lines | Cleared | 6/1/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19321 VANOWEN ST RESEDA, CA 91335 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/25/2023 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 7/25/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 7/25/2023 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2023 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/21/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 9/21/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 9/21/2023 | No Access for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 9/21/2023 | Approved | ALEXANDER HANDY |
| Pre-Inspection | 9/21/2023 | Approved | ALEXANDER HANDY |
| Wood Frame | 9/21/2023 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/28/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 9/28/2023 | Approved | ALEXANDER HANDY |
| HVAC-Final | 9/28/2023 | Corrections Issued | ALEXANDER HANDY |
| Interior/Exterior Lathing | 9/28/2023 | Partial Approval | ALEXANDER HANDY |
| Insulation | 10/13/2023 | Approved | ALEXANDER HANDY |
| Pre-Inspection | 10/13/2023 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 10/20/2023 | Approved | ALEXANDER HANDY |
| Final | 12/20/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 12/20/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 12/20/2023 | Approved | ALEXANDER HANDY |
| Final | 3/4/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 3/4/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Pre-Inspection | 3/4/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 3/12/2024 | Approved | ALEXANDER HANDY |
| Final | 3/12/2024 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 3/12/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 3/12/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 3/12/2024 | Approved | ALEXANDER HANDY |