8824 N ZELZAH AVE 91325
Certificate Information: 8824 N ZELZAH AVE 91325
- Application / Permit
- 22014-20000-03007
- Plan Check / Job No.
- B22VN09425
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) ACCESSORY LIVING QUARTERS AND STORAGE INTO A (N) ACCESSORY DWELLING UNIT, PER CA GOV. STATE CODE 65852.2(e)(1)(A), WITH A 14.5' x 21.75' PATIO ADDITION. NFPA-13D REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 10/17/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2022 | LUIS RINCON |
| Corrections Issued | 6/25/2022 | LUIS RINCON |
| Plan Check Approved | 10/14/2022 | SHANGQIN XIE |
| Issued | 10/17/2022 | APPLICANT |
| CofO in Progress | 2/12/2025 | JAVIER RAMOS JR |
| Permit Finaled | 3/4/2025 | RUBEN SALAS |
| CofO Issued | 3/4/2025 | RUBEN SALAS |
| Permit Finaled | 3/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 6/25/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 6/27/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 6/27/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 6/27/2022 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 10/11/2022 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/8/2023 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 2/8/2023 | Approved | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 3/31/2023 | Conditional Approval | ROBERT GOLD |
| Deputy Drilled-In Anchors | 4/4/2023 | Conditional Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 4/4/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 4/4/2023 | Corrections Issued | JAVIER RAMOS JR |
| Underground Mechanical | 5/1/2023 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/8/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/8/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 5/8/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/8/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/8/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/23/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Wood Frame | 5/23/2023 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/16/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 6/16/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/16/2023 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 6/28/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/28/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/6/2023 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 7/6/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 8/27/2024 | Approved | JAVIER RAMOS JR |
| Final | 8/27/2024 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 8/27/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 8/27/2024 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 8/27/2024 | Approved | JAVIER RAMOS JR |
| Final | 10/1/2024 | No Access for Inspection | JAVIER RAMOS JR |
| Final | 10/3/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 10/3/2024 | Approved | JAVIER RAMOS JR |
| Final | 10/9/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 10/9/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 10/9/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/21/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 1/21/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/21/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/12/2025 | Approved | JAVIER RAMOS JR |
| Final | 2/12/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 2/12/2025 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 2/12/2025 | Approved | JAVIER RAMOS JR |