8824 N ZELZAH AVE 91325

Certificate Information: 8824 N ZELZAH AVE 91325

Application / Permit
22014-20000-03007
Plan Check / Job No.
B22VN09425
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) ACCESSORY LIVING QUARTERS AND STORAGE INTO A (N) ACCESSORY DWELLING UNIT, PER CA GOV. STATE CODE 65852.2(e)(1)(A), WITH A 14.5' x 21.75' PATIO ADDITION. NFPA-13D REQUIRED THROUGHOUT.
Permit Issued
Issued on 10/17/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2022 APPLICANT
Assigned to Plan Check Engineer 6/22/2022 LUIS RINCON
Corrections Issued 6/25/2022 LUIS RINCON
Plan Check Approved 10/14/2022 SHANGQIN XIE
Issued 10/17/2022 APPLICANT
CofO in Progress 2/12/2025 JAVIER RAMOS JR
Permit Finaled 3/4/2025 RUBEN SALAS
CofO Issued 3/4/2025 RUBEN SALAS
Permit Finaled 3/4/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/25/2022 MEGAN GODINEZ
Sewer availability Cleared 6/25/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/27/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 6/27/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 6/27/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 6/27/2022 MEGAN GODINEZ
Hydrant and Access approval Cleared 10/11/2022 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/8/2023 Partial Approval JAVIER RAMOS JR
Sewer 2/8/2023 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 3/31/2023 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 4/4/2023 Conditional Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 4/4/2023 Not Ready for Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 4/4/2023 Corrections Issued JAVIER RAMOS JR
Underground Mechanical 5/1/2023 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 5/8/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 5/8/2023 Corrections Issued JAVIER RAMOS JR
Green Building Rough 5/8/2023 Approved JAVIER RAMOS JR
HVAC-Rough 5/8/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 5/8/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/23/2023 Not Ready for Inspection JAVIER RAMOS JR
Wood Frame 5/23/2023 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 6/16/2023 Approved JAVIER RAMOS JR
Insulation 6/16/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/16/2023 Partial Approval JAVIER RAMOS JR
Drywall Nailing 6/28/2023 Approved JAVIER RAMOS JR
Shower Pan 6/28/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 7/6/2023 Approved JAVIER RAMOS JR
Pre-Inspection 7/6/2023 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 8/27/2024 Approved JAVIER RAMOS JR
Final 8/27/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Final 8/27/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 8/27/2024 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/27/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 8/27/2024 Approved JAVIER RAMOS JR
Final 10/1/2024 No Access for Inspection JAVIER RAMOS JR
Final 10/3/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 10/3/2024 Approved JAVIER RAMOS JR
Final 10/9/2024 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 10/9/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 10/9/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/21/2025 Not Ready for Inspection JAVIER RAMOS JR
Final 1/21/2025 Not Ready for Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 1/21/2025 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 2/12/2025 Approved JAVIER RAMOS JR
Final 2/12/2025 OK to Issue CofO JAVIER RAMOS JR
Footing/Foundation/Slab 2/12/2025 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 2/12/2025 Approved JAVIER RAMOS JR