1707 S STANLEY AVE 90019

Certificate Information: 1707 S STANLEY AVE 90019

Application / Permit
22014-20000-02973
Plan Check / Job No.
B22VN09323
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR INTERIOR/EXTERIOR REMODEL TO (E) 1 STORY SFD W/ 618 SQFT ADDITION AND (N) 44 SQFT COVERED PATIO W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 11/23/2022
Issuing Office
Current Status
CofO Issued on 10/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 PETER MOSESIAN
Corrections Issued 7/17/2022 PETER MOSESIAN
Quality Review Completed 7/20/2022 OMID HEDAYAT
Building Plans Picked Up 7/25/2022 APPLICANT
Plan Check Approved 11/23/2022 PETER MOSESIAN
Issued 11/23/2022 APPLICANT
CofO in Progress 8/28/2025 WILLIAM MICHALAK
Permit Finaled 10/28/2025 CLAUDIO MORENO
CofO Issued 10/28/2025 CLAUDIO MORENO
Permit Finaled 10/28/2025 CLAUDIO MORENO

Permit Application Clearance Information

Sewer availability Cleared 8/9/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 8/10/2022 CINDY QI
Low Impact Development Cleared 8/11/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/22/2022 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/25/2023 Corrections Issued GLEN RAND
Floor/Roof Diaphrgm/Shear Wall 11/21/2023 Corrections Issued WILLIAM MICHALAK
Footing/Foundation/Slab 2/21/2024 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Barrier 2/21/2024 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Subgrade 2/21/2024 Not Ready for Inspection WILLIAM MICHALAK
Excavation/Setback/Form/Re-Bar 4/9/2024 Partial Approval WILLIAM MICHALAK
Excavation/Setback/Form/Re-Bar 4/17/2024 Partial Approval WILLIAM MICHALAK
BUILDING-Rough-Frame 4/18/2024 Corrections Issued WILLIAM MICHALAK
Green Building Rough 4/18/2024 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Rough 4/18/2024 Approved WILLIAM MICHALAK
Rough-Elec/Plmb/HVAC 4/18/2024 Not Ready for Inspection WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 6/7/2024 Not Ready for Inspection WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Not Ready for Inspection WILLIAM MICHALAK
Light Gage Steel Frame 8/26/2024 Not Ready for Inspection WILLIAM MICHALAK
BUILDING-Rough-Frame 9/6/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 9/6/2024 Corrections Issued WILLIAM MICHALAK
Rough-Elec/Plmb/HVAC 11/6/2024 Approved WILLIAM MICHALAK
Insulation 11/13/2024 Partial Approval WILLIAM MICHALAK
Insulation 11/14/2024 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 12/3/2024 Approved LUIS CORRAL
Drywall Nailing 12/11/2024 Approved WILLIAM MICHALAK
Green Building Rough 12/11/2024 Approved WILLIAM MICHALAK
Shower Pan 12/23/2024 No Access for Inspection WILLIAM MICHALAK
Shower Pan 12/24/2024 Approved WILLIAM MICHALAK
PLUMBING-Rough 2/4/2025 Partial Approval WILLIAM MICHALAK
BUILDING-Rough-Frame 7/30/2025 Not Ready for Inspection WILLIAM MICHALAK
Final 7/30/2025 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 7/30/2025 Approved WILLIAM MICHALAK
Green Building Final 7/30/2025 Corrections Issued WILLIAM MICHALAK
METHANE-Barrier 7/30/2025 Approved WILLIAM MICHALAK
METHANE-Subgrade 7/30/2025 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 7/30/2025 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 7/30/2025 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 8/28/2025 Approved WILLIAM MICHALAK
Final 8/28/2025 OK to Issue CofO WILLIAM MICHALAK
Green Building Final 8/28/2025 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 8/28/2025 SGSOV Approved WILLIAM MICHALAK