2014 E 15TH ST 90021

Certificate Information: 2014 E 15TH ST 90021

Application / Permit
22014-20000-02969
Plan Check / Job No.
B22VN09320
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
ADDITION OF EQUIPMENT LIFT & CLOSE CEILING INSIDE THE BUILDING ALSO RESTRIPE PARKING LOT AND CHANGE OF USE FROM OFFICE AND MANUFACTURING AND WAREHOUSE TO WAREHOUSE ONLY
Permit Issued
Issued on 2/17/2023
Issuing Office
Valley
Current Status
CofO in Progress on 5/14/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/15/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 MOHAMMAD ESMAILI
Corrections Issued 7/6/2022 MOHAMMAD ESMAILI
Quality Review Completed 7/8/2022 OMID HEDAYAT
Building Plans Picked Up 7/13/2022 APPLICANT
Applicant returned to address corrections 12/16/2022 MOHAMMAD ESMAILI
Application Withdrawn-Void 1/12/2023 OMID HEDAYAT
Re-Activate Application 2/13/2023 OMID HEDAYAT
Plan Check Approved 2/13/2023 MOHAMMAD ESMAILI
Issued 2/17/2023 APPLICANT
Disabled Access Plans Picked Up 10/10/2023 APPLICANT
CofO in Progress 5/14/2024 RONALD JIMENEZ
CofO in Progress 7/12/2024 ERNESTO CORRAL

Permit Application Clearance Information

Green Code Cleared 11/1/2022 MICHAEL AYERS
Miscellaneous Cleared 11/14/2022 NELSON RODRIGUEZ
Private street Cleared 11/14/2022 NELSON RODRIGUEZ
ZI Cleared 11/14/2022 NELSON RODRIGUEZ
ZI Cleared 11/14/2022 NELSON RODRIGUEZ
Roof/Waste drainage to street Cleared 11/22/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/28/2022 WALLIE JONG
ZI Cleared 1/10/2023 MIGUEL GAMBOA
ZI Cleared 1/13/2023 KENTON TRINH

Contact Information

Contractor A B F American Construction Group Inc; Lic. No.: 1055862-B 6913 WHITE OAK AVENUE      RESEDA, CA 91335
Engineer Rosepink,, Dustin; Lic. No.: S5885 24255 VIA MADRUGADA      MISSION VIEJO, CA 92692

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/7/2023 Approved JULIAN CAPUCETTI
Deputy Methane Barrier 3/31/2023 Conditional Approval RAFAEL CORTES
Deputy Drilled-In Anchors 4/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 4/11/2023 Conditional Approval JULIAN CAPUCETTI
Excavation/Setback/Form/Re-Bar 4/11/2023 Approved JULIAN CAPUCETTI
Excavation/Setback/Form/Re-Bar 4/12/2023 Approved JULIAN CAPUCETTI
Footing/Foundation/Slab 4/12/2023 Approved JULIAN CAPUCETTI
METHANE-Barrier 4/12/2023 Approved JULIAN CAPUCETTI
METHANE-Subgrade 4/12/2023 Approved JULIAN CAPUCETTI
Deputy Reinf. Masonry 4/13/2023 Conditional Approval JULIAN CAPUCETTI
Deputy Methane Barrier 4/14/2023 Conditional Approval JULIAN CAPUCETTI
Deputy Reinf. Masonry 4/14/2023 Conditional Approval JULIAN CAPUCETTI
METHANE-Rough 4/14/2023 Approved JULIAN CAPUCETTI
Reinforced Masonry Frame 4/14/2023 Partial Approval JULIAN CAPUCETTI
Deputy Reinf. Masonry 4/17/2023 Conditional Approval JULIAN CAPUCETTI
Deputy Reinf. Masonry 4/18/2023 Conditional Approval JULIAN CAPUCETTI
Masonry Wall/Backfill 4/20/2023 Approved JULIAN CAPUCETTI
Masonry Wall/Backfill 4/25/2023 Partial Approval RAFAEL CORTES
Deputy Reinf. Masonry 4/28/2023 Conditional Approval MICHAEL ROSENBERG
Structural Steel Frame 5/10/2023 Approved JULIAN CAPUCETTI
Wood Frame 5/10/2023 Approved JULIAN CAPUCETTI
Final 6/22/2023 Not Ready for Inspection RAMAZANALI ALMASI
Reinforced Masonry Frame 6/22/2023 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 6/22/2023 SGSOV Not Ready RAMAZANALI ALMASI
Smoke Detectors 6/22/2023 Not Ready for Inspection RAMAZANALI ALMASI
Final 6/28/2023 Partial Approval JULIAN CAPUCETTI
Reinforced Masonry Frame 6/28/2023 Approved JULIAN CAPUCETTI
SGSOV-Seismic Gas S/O Valve 6/28/2023 SGSOV No Gas JULIAN CAPUCETTI
Smoke Detectors 6/28/2023 Approved JULIAN CAPUCETTI
Final 5/9/2024 Conditional Approval RONALD JIMENEZ
Final 5/13/2024 Partial Inspection RONALD JIMENEZ
Final 7/12/2024 Corrections Issued RONALD JIMENEZ