15711 W TUPPER ST 91343

Certificate Information: 15711 W TUPPER ST 91343

Application / Permit
22014-20000-02965
Plan Check / Job No.
B22VN09301
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
11' X 16'-2" ADDITION OF BEDROOM TO THE (E) SFD.
Permit Issued
Issued on 12/22/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2022 APPLICANT
Assigned to Plan Check Engineer 6/16/2022 PINANK PATEL
Corrections Issued 6/22/2022 PINANK PATEL
Building Plans Picked Up 6/24/2022 APPLICANT
Applicant returned to address corrections 12/19/2022 ISIS ARGUETA
Plan Check Approved 12/22/2022 SERGIO MUNIZ
Issued 12/22/2022 APPLICANT
CofO in Progress 7/19/2023 JUAN VALENZUELA
Permit Finaled 8/8/2023 RUBEN SALAS
CofO Issued 8/8/2023 RUBEN SALAS
Permit Finaled 8/8/2023 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/12/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 7/12/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 11/1/2022 ERIK BEASLEY

Contact Information

Architect Snead,, George Thomas; Lic. No.: C13902 269 SO BEVERLY DRIVE 360      BEVERLY HILLS, CA 90212
Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/5/2023 Conditional Approval DAVID MATSON
Deputy Reinf. Concrete 4/5/2023 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 4/5/2023 Approved JUAN VALENZUELA
Deputy Reinf. Concrete 4/7/2023 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 4/13/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 4/25/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 4/25/2023 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Approved RAUL OLAGI
HVAC-Rough 4/25/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 4/25/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/15/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 5/15/2023 Approved RAUL OLAGI
Green Building Rough 5/15/2023 Approved RAUL OLAGI
HVAC-Rough 5/15/2023 Approved RAUL OLAGI
MERV13>=Rough 5/15/2023 Approved RAUL OLAGI
Insulation 6/1/2023 Approved RAUL OLAGI
Drywall Nailing 6/7/2023 Approved RAUL OLAGI
ELECTRICAL-Final 7/18/2023 Approved JUAN VALENZUELA
Final 7/18/2023 OK to Issue CofO JUAN VALENZUELA
Green Building Final 7/18/2023 Approved JUAN VALENZUELA
HVAC-Final 7/18/2023 Approved JUAN VALENZUELA
MERV13>=Final 7/18/2023 Approved JUAN VALENZUELA
PLUMBING-Final 7/18/2023 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 7/18/2023 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 7/18/2023 Approved JUAN VALENZUELA