6717 N KATHERINE AVE 91405
Certificate Information: 6717 N KATHERINE AVE 91405
- Application / Permit
- 22014-20000-02961
- Plan Check / Job No.
- B22VN09298
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 10/7/2022
- Issuing Office
- Current Status
- CofO Issued on 10/17/2023
- Certificate of Occupancy
- 245262 - CofO Issued More Information
- 245262 - CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | DANIEL YIP |
| Corrections Issued | 6/25/2022 | DANIEL YIP |
| Applicant returned to address corrections | 7/14/2022 | DANIEL YIP |
| Plan Check Approved | 9/30/2022 | DANIEL YIP |
| Issued | 10/7/2022 | APPLICANT |
| CofO in Progress | 8/25/2023 | RYAN SALAZAR |
| Permit Finaled | 10/17/2023 | RUBEN SALAS |
| CofO Issued | 10/17/2023 | RUBEN SALAS |
| Permit Finaled | 10/17/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/29/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2022 | DAGOVERTO GUERRERO |
| Address approval | Cleared | 9/20/2022 | CARLOS AGUILERA |
| HPOZ | Cleared | 9/20/2022 | SUKI GERSHENHORN |
| Sewer availability | Cleared | 9/27/2022 | DAGOVERTO GUERRERO |
| Public Works-Highway Ded. | Cleared | 10/19/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 10/19/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 10/19/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | D B Builders Inc; Lic. No.: 812896-B | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/29/2022 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 2/2/2023 | Conditional Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 4/6/2023 | Approved | RYAN SALAZAR |
| Deputy Wood Construction | 4/7/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 5/8/2023 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 5/8/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 5/8/2023 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 5/16/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 5/30/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 5/30/2023 | Approved | RYAN SALAZAR |
| Insulation | 5/30/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/30/2023 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 6/8/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 6/8/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/23/2023 | Approved | RYAN SALAZAR |
| Pre-Inspection | 8/1/2023 | Partial Inspection | RYAN SALAZAR |
| ELECTRICAL-Final | 8/24/2023 | Approved | RYAN SALAZAR |
| Final | 8/24/2023 | OK to Issue CofO | RYAN SALAZAR |
| HVAC-Final | 8/24/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 8/24/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 8/24/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 8/24/2023 | Approved | RYAN SALAZAR |