12051 N SUSAN DR 91344

Certificate Information: 12051 N SUSAN DR 91344

Application / Permit
22014-20000-02952
Plan Check / Job No.
B22VN09291
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Addition of 320 Sq.ft. To existing Kitchen
Permit Issued
Issued on 10/28/2022
Issuing Office
Current Status
CofO Issued on 12/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 NGHI SU
Corrections Issued 8/9/2022 NGHI SU
Quality Review Completed 8/9/2022 GARO TELMI
Applicant returned to address corrections 10/5/2022 NGHI SU
Applicant returned to address corrections 10/19/2022 NGHI SU
Plan Check Approved 10/20/2022 NGHI SU
Issued 10/28/2022 APPLICANT
CofO in Progress 12/10/2025 CHRISTOPHER ROJAS
Permit Finaled 12/26/2025 RUBEN SALAS
CofO Issued 12/26/2025 RUBEN SALAS
Permit Finaled 12/26/2025 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/19/2022 LANNY MERRICK
BHO/Hillside ordinance Cleared 8/29/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/29/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/29/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/29/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/29/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/31/2022 LEE GUILBEAUX
Miscellaneous Cleared 9/1/2022 DANG NGUYEN
Miscellaneous Cleared 9/1/2022 DANG NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/19/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 12/19/2024 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 1/14/2025 Approved JAVIER RAMOS JR
HVAC-Rough 1/14/2025 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 1/14/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Corrections Issued JACK KARGODORIAN
Insulation 3/3/2025 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/25/2025 Partial Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/27/2025 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/27/2025 Partial Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 4/2/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/2/2025 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Approved CHRISTOPHER ROJAS
Insulation 4/7/2025 Approved CHRISTOPHER ROJAS
Shower Pan 4/7/2025 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 4/17/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 4/17/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Shower Pan 4/17/2025 Corrections Issued NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 5/8/2025 Partial Approval LOUIS ESCOTO
BUILDING-Rough-Frame 5/14/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 5/14/2025 Partial Approval CHRISTOPHER ROJAS
Shower Pan 7/9/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 7/14/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 7/14/2025 Approved MICHAEL CORTEZ
Floor/Roof Diaphrgm/Shear Wall 7/21/2025 Corrections Issued CHRISTOPHER ROJAS
Final 8/5/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/5/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 8/5/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 8/5/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 8/5/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 8/5/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/20/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Pre-Inspection 10/27/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Final 11/5/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/5/2025 Approved CHRISTOPHER ROJAS
Green Building Final 11/5/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 11/5/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 11/5/2025 Approved CHRISTOPHER ROJAS
Final 12/10/2025 OK to Issue CofO CHRISTOPHER ROJAS