6718 N JUMILLA AVE 91306

Certificate Information: 6718 N JUMILLA AVE 91306

Application / Permit
22014-20000-02943
Plan Check / Job No.
B22VN09248
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14'-6" X 6'-0" ADDITION OF A NEW BATHROOM TO THE (E) SFD. ALL WORK PER WFPP
Permit Issued
Issued on 7/12/2022
Issuing Office
Current Status
CofO Issued on 3/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2022 APPLICANT
Assigned to Plan Check Engineer 6/16/2022 LUISANGEL VALENZUELA
Corrections Issued 6/18/2022 LUISANGEL VALENZUELA
Issued 7/12/2022 APPLICANT
Building Plans Picked Up 7/14/2022 APPLICANT
CofO in Progress 3/6/2023 ALEXANDER HANDY
Permit Finaled 3/10/2023 JOHN JANSON
CofO Issued 3/10/2023 JOHN JANSON
Permit Finaled 3/10/2023 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/24/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/25/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 6/25/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 6/25/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 6/25/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Enclosure/Fence 8/30/2022 No Access for Inspection STEVEN BACK
Excavation/Setback/Form/Re-Bar 8/30/2022 No Access for Inspection STEVEN BACK
PLUMBING-Rough 8/30/2022 No Access for Inspection STEVEN BACK
Footing/Foundation/Slab 12/30/2022 No Access for Inspection ALEXANDER HANDY
Footing/Foundation/Slab 1/12/2023 Approved ALEXANDER HANDY
Insulation 1/24/2023 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 1/24/2023 Approved ALEXANDER HANDY
Wood Frame 1/24/2023 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 1/30/2023 Partial Approval ALEXANDER HANDY
Green Building Rough 1/30/2023 Not Ready for Inspection ALEXANDER HANDY
Rough-Elec/Plmb/HVAC 1/30/2023 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 2/9/2023 Approved ALEXANDER HANDY
Green Building Rough 2/9/2023 Approved ALEXANDER HANDY
Insulation 2/9/2023 Approved ALEXANDER HANDY
Interior/Exterior Lathing 2/9/2023 Partial Approval ALEXANDER HANDY
Shower Pan 2/9/2023 Approved ALEXANDER HANDY
Drywall Nailing 2/14/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 2/14/2023 Approved JUSTIN HAWLEY
Final 3/1/2023 Not Ready for Inspection ALEXANDER HANDY
Green Building Final 3/1/2023 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 3/1/2023 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 3/1/2023 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Final 3/3/2023 Approved ALEXANDER HANDY
Final 3/3/2023 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 3/3/2023 Approved ALEXANDER HANDY
PLUMBING-Final 3/3/2023 Approved ALEXANDER HANDY
Smoke Detectors 3/3/2023 Approved ALEXANDER HANDY