13060 W DEBELL ST 91331
Certificate Information: 13060 W DEBELL ST 91331
- Application / Permit
- 22014-20000-02911
- Plan Check / Job No.
- B22VN09162
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXTERIOR ALTERATION TO REMOVE PORTIONS OF THE REAR PATIO COVER AND ADDITION OF INTERIOR CONDITIONED SPACE.
- Permit Issued
- Issued on 8/30/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2022 | LUIS RINCON |
| Corrections Issued | 6/13/2022 | LUIS RINCON |
| Building Plans Picked Up | 6/17/2022 | APPLICANT |
| Plan Check Approved | 8/30/2022 | JOSEPH RAFOLS |
| Issued | 8/30/2022 | APPLICANT |
| CofO in Progress | 2/27/2025 | MICHEL ABAJAN |
| Permit Finaled | 3/11/2025 | RUBEN SALAS |
| CofO Issued | 3/11/2025 | RUBEN SALAS |
| Permit Finaled | 3/11/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/1/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/9/2024 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 12/2/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/21/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/21/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 1/21/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 1/21/2025 | Approved | MICHEL ABAJAN |
| Insulation | 1/27/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/27/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 2/4/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 2/26/2025 | Approved | MICHEL ABAJAN |
| Final | 2/26/2025 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 2/26/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 2/26/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 2/26/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 2/26/2025 | Partial Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 2/26/2025 | Approved | MICHEL ABAJAN |