136 S WINDSOR BLVD 90004

Certificate Information: 136 S WINDSOR BLVD 90004

Application / Permit
22014-20000-02882
Plan Check / Job No.
B22VN09090
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
IRR. SHAPED 17'-2" x 17'-2" (150 SF) ADDITION TO AND CONVERT (E) 1-STORY DET. GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A); NFPA 13D THRU-OUT
Permit Issued
Issued on 12/13/2022
Issuing Office
Current Status
CofO Corrected on 8/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 COLIN LOREDO
Corrections Issued 7/12/2022 COLIN LOREDO
Quality Review Completed 7/22/2022 OMID HEDAYAT
Building Plans Picked Up 7/22/2022 APPLICANT
Applicant returned to address corrections 11/22/2022 SEAN SHAHMIRI
Plan Check Approved 12/13/2022 SEAN SHAHMIRI
Issued 12/13/2022 APPLICANT
CofO in Progress 11/1/2024 BRENDAN MORELLI
CofO Issued-Status Void 11/4/2024 DEROLD HAUFF
Permit Finaled-Status Void 11/4/2024 DEROLD HAUFF
Re-Activate Permit 6/23/2025 DEROLD HAUFF
CofO Corrected 8/20/2025 DEROLD HAUFF
Permit Finaled 8/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/8/2022 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 10/8/2022 CHRISTOPHER ROCHA
HPOZ Cleared 11/15/2022 DAMIAN GATTO
Eng Process Fee Ord 176,300 Cleared 11/18/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 11/18/2022 CHRISTOPHER ROCHA
Construction within easement Cleared 11/22/2022 RIDWAN HARDY

Contact Information

Architect Bertram,, John; Lic. No.: C29063 673 N BERENDO STREET      LOS ANGELES, CA 90004
Contractor Boswell Construction Inc; Lic. No.: 934480-B 14611 VENTURA BLVD 2ND FLOOR      SHERMAN OAKS, CA 91403
Engineer Peck,, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/1/2023 Approved JEFFREY MEAD
Deputy Drilled-In Anchors 5/11/2023 Partial Approval JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 5/11/2023 Approved JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 6/1/2023 Approved JEFFREY MEAD
PLUMBING-Rough 8/1/2023 Approved JEFFREY MEAD
ELECTRICAL-Rough 8/8/2023 Corrections Issued JEFFREY MEAD
Deputy Steel/Welding 8/15/2023 Partial Approval JEFFREY MEAD
HVAC-Rough 9/21/2023 Corrections Issued JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 11/20/2023 Conditional Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Approved JEFFREY MEAD
BUILDING-Rough-Frame 12/4/2023 Approved JEFFREY MEAD
Green Building Rough 12/4/2023 Approved JEFFREY MEAD
Insulation 12/4/2023 Approved JEFFREY MEAD
Verify Sprinkler Sign Off 12/4/2023 Approved JEFFREY MEAD
Drywall Nailing 12/12/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 1/12/2024 Partial Approval JEFFREY MEAD
Shower Pan 1/12/2024 Approved JEFFREY MEAD
PLUMBING-Rough 4/8/2024 Partial Approval JEFFREY MEAD
Sewer 4/8/2024 Approved JEFFREY MEAD
Interior/Exterior Lathing 6/5/2024 Approved JEFFREY MEAD
Gas Test 7/16/2024 Approved JOSEPH MCGARRY
HVAC-Final 9/27/2024 Approved JOSE MACIAS
ELECTRICAL-Final 10/11/2024 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Final 10/25/2024 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 10/25/2024 Approved JEFFREY MEAD
Green Building Final 10/25/2024 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 10/25/2024 SGSOV Approved JEFFREY MEAD
Smoke Detectors 10/25/2024 Approved JEFFREY MEAD
ELECTRICAL-Final 10/28/2024 Partial Approval ENRIQUE MIRELES
PLUMBING-Final 10/28/2024 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 10/30/2024 Approved BRENDAN MORELLI
ELECTRICAL-Final 10/31/2024 Approved BRENDAN MORELLI
Final 10/31/2024 OK to Issue CofO BRENDAN MORELLI