134 S WINDSOR BLVD 90004

Certificate Information: 134 S WINDSOR BLVD 90004

Application / Permit
22014-20000-02881
Plan Check / Job No.
B22VN09090
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL WITH REAR ADDITION (23 sf) TO THE (E) 2-STORY SINGLE FAMILY DWELLING, CONVERT ATTIC TO (N) HABITABLE SPACE (618 sf), CONVERT BASEMENT INTO LAUNDRY ROOM WITH STORAGE. NFPA 13D THRU-OUT
Permit Issued
Issued on 12/13/2022
Issuing Office
Current Status
CofO Corrected on 8/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 COLIN LOREDO
Corrections Issued 7/12/2022 COLIN LOREDO
Quality Review Completed 7/22/2022 OMID HEDAYAT
Building Plans Picked Up 7/22/2022 APPLICANT
Applicant returned to address corrections 11/22/2022 SEAN SHAHMIRI
Plan Check Approved 12/13/2022 SEAN SHAHMIRI
Issued 12/13/2022 APPLICANT
CofO in Progress 8/21/2024 JEFFREY MEAD
CofO Issued-Status Void 12/26/2024 DEROLD HAUFF
Permit Finaled-Status Void 12/26/2024 DEROLD HAUFF
Re-Activate Permit 6/23/2025 DEROLD HAUFF
Permit Finaled 8/20/2025 DEROLD HAUFF
CofO Corrected 8/20/2025 DEROLD HAUFF
Permit Finaled 8/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/8/2022 CHRISTOPHER ROCHA
HPOZ Cleared 11/7/2022 DAMIAN GATTO
Sewer availability Cleared 11/10/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 11/18/2022 CHRISTOPHER ROCHA

Contact Information

Architect Bertram,, John; Lic. No.: C29063 673 N BERENDO STREET      LOS ANGELES, CA 90004
Contractor Boswell Construction Inc; Lic. No.: 934480-B 14611 VENTURA BLVD 2ND FLOOR      SHERMAN OAKS, CA 91403
Engineer Peck,, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/12/2023 Approved JEFFREY MEAD
Deputy Wood Construction 3/24/2023 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Partial Approval JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 4/3/2023 Partial Approval JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 4/6/2023 Partial Approval JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 4/13/2023 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 4/17/2023 Partial Approval JEFFREY MEAD
Deputy Drilled-In Anchors 4/27/2023 Conditional Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 5/1/2023 Partial Approval JEFFREY MEAD
PLUMBING-Rough 5/16/2023 Partial Approval JEFFREY MEAD
Deputy Drilled-In Anchors 5/18/2023 Partial Approval JEFFREY MEAD
Deputy Drilled-In Anchors 6/1/2023 Partial Approval JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 6/1/2023 Approved JEFFREY MEAD
Deputy Drilled-In Anchors 6/6/2023 Partial Approval JEFFREY MEAD
PLUMBING-Rough 8/1/2023 Approved JEFFREY MEAD
ELECTRICAL-Rough 8/8/2023 Corrections Issued JEFFREY MEAD
HVAC-Rough 9/21/2023 Corrections Issued JEFFREY MEAD
ELECTRICAL-Rough 9/28/2023 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Approved JEFFREY MEAD
HVAC-Rough 9/28/2023 Not Ready for Inspection JEFFREY MEAD
Underground Mechanical 9/28/2023 Approved JEFFREY MEAD
Verify Sprinkler Sign Off 9/28/2023 Partial Approval JEFFREY MEAD
Shower Pan 10/4/2023 Approved JEFFREY MEAD
Deputy Steel/Welding 10/18/2023 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 10/23/2023 Partial Approval JEFFREY MEAD
Green Building Rough 10/23/2023 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 10/27/2023 Approved JEFFREY MEAD
Green Building Rough 10/27/2023 Approved JEFFREY MEAD
Insulation 11/9/2023 Approved JEFFREY MEAD
Drywall Nailing 11/20/2023 Partial Approval JEFFREY MEAD
Interior/Exterior Lathing 11/20/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 12/13/2023 Not Ready for Inspection JEFFREY MEAD
Interior/Exterior Lathing 12/15/2023 Partial Approval JEFFREY MEAD
Interior/Exterior Lathing 12/18/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 1/12/2024 Approved JEFFREY MEAD
Special/Order Compliance 3/19/2024 Approved JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 4/8/2024 Approved JEFFREY MEAD
PLUMBING-Rough 4/8/2024 Not Ready for Inspection JEFFREY MEAD
Sewer 4/8/2024 Approved JEFFREY MEAD
Underground Mechanical 4/22/2024 Approved JEFFREY MEAD
Service/Power Release 6/13/2024 Approved JEFFREY MEAD
Gas Test 7/16/2024 Approved JOSEPH MCGARRY
Service/Power Release 7/16/2024 Approved JOAQUIN GREENOUGH
HVAC-Final 7/31/2024 Approved JEFFREY MEAD
Special/Order Compliance 7/31/2024 Partial Approval NICHOLAS LOPEZ
ELECTRICAL-Final 8/8/2024 Approved JEFFREY MEAD
PLUMBING-Final 8/9/2024 Approved JEFFREY MEAD
Drywall Nailing 8/13/2024 Approved BRENDAN MORELLI
Final 8/13/2024 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 8/13/2024 Approved BRENDAN MORELLI
Green Building Final 8/13/2024 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 8/13/2024 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 8/13/2024 Approved BRENDAN MORELLI
Final 8/16/2024 Corrections Issued ALIZAH MAYAGOITIA
Final 8/20/2024 OK to Issue CofO JEFFREY MEAD