6835 N LINDLEY AVE 91335
Certificate Information: 6835 N LINDLEY AVE 91335
- Application / Permit
- 22014-20000-02880
- Plan Check / Job No.
- B22VN09053
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 9'-6" X 8'-6" BATHROOM ADDITION TO (E) SFD. ALL WORK PER WFPP
- Permit Issued
- Issued on 9/30/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 6/13/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 7/25/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 7/26/2022 | APPLICANT |
| Issued | 9/30/2022 | APPLICANT |
| CofO in Progress | 5/30/2023 | JEFFREY BULL |
| Permit Finaled | 4/17/2024 | DANIEL ORRANTE |
| CofO Issued | 4/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 7/13/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/14/2023 | Approved | JEFFREY BULL |
| Sewer | 3/14/2023 | Approved | JEFFREY BULL |
| Special/Order Compliance | 3/14/2023 | Partial Inspection | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 3/17/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 3/17/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 4/10/2023 | Approved | SEAN WIRCH |
| Green Building Rough | 4/10/2023 | Approved | SEAN WIRCH |
| Insulation | 4/10/2023 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 4/10/2023 | Partial Approval | SEAN WIRCH |
| Rough-Elec/Plmb/HVAC | 4/10/2023 | Approved | SEAN WIRCH |
| Shower Pan | 4/10/2023 | Approved | SEAN WIRCH |
| Drywall Nailing | 4/13/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 5/26/2023 | Approved | JEFFREY BULL |
| Final | 5/26/2023 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 5/26/2023 | Approved | JEFFREY BULL |
| HVAC-Final | 5/26/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 5/26/2023 | Approved | JEFFREY BULL |
| Smoke Detectors | 5/26/2023 | Approved | JEFFREY BULL |