11853 W SYLVAN ST 91606

Certificate Information: 11853 W SYLVAN ST 91606

Application / Permit
22014-20000-02874
Plan Check / Job No.
B22VN09048
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. Converting existing detached garage to an ADU with new addition.
Permit Issued
Issued on 9/5/2023
Issuing Office
Current Status
CofO Issued on 5/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2022 APPLICANT
Assigned to Plan Check Engineer 6/17/2022 SAMUEL GONZALEZ
Corrections Issued 6/18/2022 SAMUEL GONZALEZ
Applicant returned to address corrections 3/2/2023 SAMUEL GONZALEZ
Plan Check Approved 4/13/2023 KEVIN MORALES
Issued 9/5/2023 APPLICANT
CofO in Progress 4/21/2025 JOSE AVILA
Permit Finaled 5/13/2025 RUBEN SALAS
CofO Issued 5/13/2025 RUBEN SALAS
Permit Finaled 5/13/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 8/12/2022 RIDWAN HARDY
Low Impact Development Cleared 1/31/2023 ANTHONY VARGAS
Address approval Cleared 2/7/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 2/7/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 2/13/2023 COLIN LOREDO
Sewer availability Cleared 2/13/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 11/7/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 11/7/2024 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 11/12/2024 Approved JOSE AVILA
Footing/Foundation/Slab 11/13/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Approved JOSE AVILA
PLUMBING-Rough 12/16/2024 Approved JOSE AVILA
ELECTRICAL-Rough 12/26/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/26/2024 Corrections Issued JOSE AVILA
HVAC-Rough 12/26/2024 Conditional Approval JOSE AVILA
BUILDING-Rough-Frame 12/31/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 12/31/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 12/31/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
Insulation 1/3/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/3/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Drywall Nailing 1/7/2025 Approved MICHAEL CORTEZ
Shower Pan 1/7/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 1/14/2025 Approved ROBERT GOLD
ELECTRICAL-Rough 1/22/2025 Approved MATTHEW NELSON
PLUMBING-Rough 1/22/2025 Partial Approval MATTHEW NELSON
ELECTRICAL-Final 3/12/2025 Corrections Issued JOSE AVILA
HVAC-Final 3/12/2025 Corrections Issued JOSE AVILA
PLUMBING-Final 3/12/2025 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV Not Ready JOSE AVILA
Smoke Detectors 3/12/2025 Approved JOSE AVILA
ELECTRICAL-Final 4/4/2025 Approved JOSE AVILA
HVAC-Final 4/4/2025 Approved JOSE AVILA
PLUMBING-Final 4/4/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Approved JOSE AVILA
Service/Power Release 4/4/2025 Approved JOSE AVILA
Final 4/21/2025 OK to Issue CofO JOSE AVILA