4745 N POE AVE 91364
Certificate Information: 4745 N POE AVE 91364
- Application / Permit
- 22014-20000-02872
- Plan Check / Job No.
- B22VN09047
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (32'5" x 51'-3") IRR SHAPED TO ENLARGE (3) BEDROOMS, (2) BATHROOMS , MASTER CLOSET AND NEW 19'11" X 16'4" TO ENLARGE THE KITCHEN , NEW 13'2" X 32'6" REAR PATIO ADDITION , MAJOR REMODEL TO (E) 1-STORY SINGLE FAMILY DWELLING, WITH NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 10/6/2022
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 5/11/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | TROY DEGUZMAN |
| Corrections Issued | 7/27/2022 | TROY DEGUZMAN |
| Quality Review Completed | 7/28/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 8/1/2022 | APPLICANT |
| Applicant returned to address corrections | 9/22/2022 | RARES BODEA |
| Plan Check Approved | 10/4/2022 | RARES BODEA |
| Issued | 10/6/2022 | APPLICANT |
| CofO in Progress | 5/11/2026 | SEAN WIRCH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/27/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 7/27/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 7/27/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 7/27/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 7/27/2022 | JOSE DUARTE-DIAZ |
| GPI Written Notices | Cleared | 7/27/2022 | ALEXANDER HELFER |
| Grading Pre-Inspection | Cleared | 7/27/2022 | ALEXANDER HELFER |
| Sewer availability | Cleared | 7/27/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 8/9/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/9/2022 | JOHN LIN |
| Hydrant and Access approval | Cleared | 9/6/2022 | JOHN CONNEALLY |
Contact Information
| Architect | Mizuki,, Steve Massanori; Lic. No.: C22676 | 2155 VERDUGO BLVD # 330 MONTROSE, CA 91020 |
| Contractor | Quality First Builders Inc; Lic. No.: 990316-B | 5530 CORBIN AVE 345 TARZANA, CA 91356 |
| Engineer | Durand,, Paul H; Lic. No.: S4222 | 611 N G ST OXNARD, CA 93030 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/19/2022 | Partial Approval | PETER FOLLING |
| Deputy Drilled-In Anchors | 10/25/2022 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 10/27/2022 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 1/27/2023 | Approved | PETER FOLLING |
| HVAC-Rough | 1/27/2023 | Corrections Issued | PETER FOLLING |
| PLUMBING-Rough | 1/27/2023 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 2/21/2023 | Approved | SEAN WIRCH |
| Green Building Rough | 2/21/2023 | Approved | SEAN WIRCH |
| HVAC-Rough | 2/21/2023 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 2/21/2023 | Partial Approval | SEAN WIRCH |
| Verify Sprinkler Sign Off | 2/21/2023 | Approved | SEAN WIRCH |
| Insulation | 2/24/2023 | Approved | PETER FOLLING |
| Drywall Nailing | 3/8/2023 | Approved | PETER FOLLING |
| Shower Pan | 4/6/2023 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 4/20/2023 | Approved | PETER FOLLING |
| Deputy Reinf. Concrete | 7/12/2023 | No Access for Inspection | PETER FOLLING |
| Gas Test | 7/24/2023 | Corrections Issued | PETER FOLLING |
| Service/Power Release | 7/24/2023 | Not Ready for Inspection | PETER FOLLING |
| Final | 2/21/2024 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 2/21/2024 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Approved | MORRIS JACKSON |
| Smoke Detectors | 2/21/2024 | Approved | MORRIS JACKSON |
| Final | 7/29/2024 | Corrections Issued | JOHN HAYES |
| Final | 1/10/2025 | No Access for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 5/5/2026 | Approved | SEAN WIRCH |
| Final | 5/5/2026 | OK to Issue CofO | SEAN WIRCH |
| HVAC-Final | 5/5/2026 | Approved | SEAN WIRCH |
| PLUMBING-Final | 5/5/2026 | Approved | SEAN WIRCH |