4252 N TOSCA ROAD 91364
Certificate Information: 4252 N TOSCA ROAD 91364
- Application / Permit
- 22014-20000-02866
- Plan Check / Job No.
- B22VN09033
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* ADDITION AND REMODEL OF (E) 1-STORY SFD WITH (E) ATTACHED CARPORT.
- Permit Issued
- Issued on 8/19/2022
- Issuing Office
- Current Status
- CofO Issued on 9/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | VIVIAN LAO |
| Corrections Issued | 6/17/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 8/17/2022 | VIVIAN LAO |
| Plan Check Approved | 8/19/2022 | VIVIAN LAO |
| Issued | 8/19/2022 | APPLICANT |
| CofO in Progress | 8/20/2025 | JOHN HAYES |
| Permit Finaled | 9/12/2025 | MICHAEL PELHAM |
| CofO Issued | 9/12/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/12/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/21/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2022 | MEGAN GODINEZ |
| Grading Pre-Inspection | Cleared | 6/22/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 6/22/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 6/22/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 6/22/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 6/22/2022 | MEGAN GODINEZ |
| Specific Plan | Cleared | 8/10/2022 | OLGA AYALA |
| Specific Plan | Cleared | 8/10/2022 | OLGA AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zandian,, Rashid; Lic. No.: C87581 | 10303 CAMINITO ARALIA 98 SAN DIEGO, CA 92131 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/3/2022 | Approved | JOHN KIDWELL |
| Underground Mechanical | 10/3/2022 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 11/28/2022 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 11/28/2022 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 11/28/2022 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 11/28/2022 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 11/28/2022 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/12/2022 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 12/12/2022 | Approved | PETER FOLLING |
| Green Building Rough | 12/12/2022 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 12/12/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 12/12/2022 | Not Ready for Inspection | PETER FOLLING |
| Wood Frame | 12/12/2022 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 12/22/2022 | Not Ready for Inspection | PETER FOLLING |
| Green Building Rough | 12/22/2022 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 12/22/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 12/22/2022 | Approved | PETER FOLLING |
| Wood Frame | 12/22/2022 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 12/28/2022 | Approved | PETER FOLLING |
| Green Building Rough | 12/28/2022 | Approved | PETER FOLLING |
| HVAC-Rough | 12/28/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 12/28/2022 | Partial Approval | PETER FOLLING |
| Wood Frame | 12/28/2022 | Approved | PETER FOLLING |
| Insulation | 1/24/2023 | Corrections Issued | PETER FOLLING |
| Insulation | 2/7/2023 | Approved | PETER FOLLING |
| Drywall Nailing | 2/22/2023 | Approved | PETER FOLLING |
| Shower Pan | 2/22/2023 | Approved | PETER FOLLING |
| Shower Pan | 5/10/2023 | Approved | PETER FOLLING |
| Footing/Foundation/Slab | 6/29/2023 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 8/21/2023 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 1/23/2025 | No Access for Inspection | JOHN HAYES |
| Gas Test | 1/23/2025 | No Access for Inspection | JOHN HAYES |
| PLUMBING-Rough | 1/23/2025 | No Access for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 6/26/2025 | Approved | JOHN HAYES |
| Final | 6/26/2025 | Corrections Issued | JOHN HAYES |
| Green Building Final | 6/26/2025 | Approved | JOHN HAYES |
| HVAC-Final | 6/26/2025 | Approved | JOHN HAYES |
| PLUMBING-Final | 6/26/2025 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 6/26/2025 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 6/26/2025 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 8/20/2025 | Approved | JOHN HAYES |
| Final | 8/20/2025 | OK to Issue CofO | JOHN HAYES |
| HVAC-Final | 8/20/2025 | Approved | JOHN HAYES |
| PLUMBING-Final | 8/20/2025 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/20/2025 | SGSOV Not Required | JOHN HAYES |