8818 N OAK PARK AVE 91325

Certificate Information: 8818 N OAK PARK AVE 91325

Application / Permit
22014-20000-02833
Plan Check / Job No.
B22VN08945
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION 556 SF (EXISTING BREEZEWAY IS INCLUDED IN NEW ADDITION)
Permit Issued
Issued on 9/8/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2022 APPLICANT
Assigned to Plan Check Engineer 6/15/2022 ARTIN ZARUKIAN
Corrections Issued 6/16/2022 ARTIN ZARUKIAN
Building Plans Picked Up 6/17/2022 APPLICANT
Plan Check Approved 7/29/2022 YAQUB MIRZA
Issued 9/8/2022 APPLICANT
CofO in Progress 7/21/2023 JAVIER RAMOS JR
Permit Finaled 8/30/2023 RUBEN SALAS
CofO Issued 8/30/2023 RUBEN SALAS
Permit Finaled 8/30/2023 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/14/2022 MEGAN GODINEZ
Sewer availability Cleared 7/14/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 7/28/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yu,, Jennifer Arianna; Lic. No.: C79156 3828 EARLE AVE      ROSEMEAD, CA 91770

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/16/2022 Conditional Approval MICHAEL SMITH
Excavation/Setback/Form/Re-Bar 11/22/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 11/29/2022 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 11/29/2022 Approved JAVIER RAMOS JR
Insulation 12/5/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 12/5/2022 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 12/6/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Corrections Issued JAVIER RAMOS JR
Deputy Wood Construction 12/28/2022 Conditional Approval MICHAEL SMITH
BUILDING-Rough-Frame 1/20/2023 Partial Approval JAVIER RAMOS JR
Green Building Rough 1/20/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 1/20/2023 Partial Approval JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 1/20/2023 Approved JAVIER RAMOS JR
Insulation 2/1/2023 Approved JAVIER RAMOS JR
Deputy Wood Construction 2/7/2023 Approved JAVIER RAMOS JR
Drywall Nailing 2/7/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Approved JAVIER RAMOS JR
Shower Pan 3/22/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/23/2023 Approved JOHN COLEMAN
BUILDING-Rough-Frame 7/17/2023 Approved JAVIER RAMOS JR
Final 7/17/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 7/17/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 7/17/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 7/17/2023 Approved JAVIER RAMOS JR
Final 7/20/2023 OK to Issue CofO JAVIER RAMOS JR