11725-11727 N BRUSSELS AVE 91342
Certificate Information: 11725-11727 N BRUSSELS AVE 91342
- Application / Permit
- 22014-20000-02806
- Plan Check / Job No.
- B22VN08882
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 24' X 20' (405 SF) IRR. PORTION OF THE (E) ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e), AND CONVERT 6' X 12'-9" (75 SF) PORTION OF GARAGE INTO A LAUNDRY ROOM. CONVERT 10' X 18' (E) PATIO COVER INTO (N) BEDROOM. WORK PER ENGINEER.
- Permit Issued
- Issued on 12/22/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | LUIS RINCON |
| Corrections Issued | 6/17/2022 | LUIS RINCON |
| Building Plans Picked Up | 6/21/2022 | APPLICANT |
| Issued | 12/22/2022 | APPLICANT |
| CofO in Progress | 2/6/2025 | MICHEL ABAJAN |
| Permit Finaled | 2/13/2025 | RUBEN SALAS |
| CofO Issued | 2/13/2025 | RUBEN SALAS |
| Permit Finaled | 2/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 7/28/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 12/20/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 12/20/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 12/20/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 12/20/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Vicsinc.Com; Lic. No.: 1002544-B | P O BOX 950931 MISSION HILLS, CA 91395 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/23/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/23/2023 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 8/31/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 8/31/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 8/31/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/18/2023 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/18/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/18/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 9/18/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 9/18/2023 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/22/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/22/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/22/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 9/22/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/22/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 12/13/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 12/13/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 12/13/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 12/13/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/13/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/13/2024 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 12/13/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/22/2025 | Approved | MICHEL ABAJAN |
| Final | 1/22/2025 | Corrections Issued | MICHEL ABAJAN |
| Final | 2/5/2025 | OK to Issue CofO | MICHEL ABAJAN |