5158 N LOLETA AVE 90041
Certificate Information: 5158 N LOLETA AVE 90041
- Application / Permit
- 22014-20000-02800
- Plan Check / Job No.
- B22VN08875
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 2-STORY ACCESSORY DWELLING UNIT AND STORAGE TO (E) GARAGE per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 11/30/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 7/10/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 7/21/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 7/22/2022 | APPLICANT |
| Applicant returned to address corrections | 11/7/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 11/30/2022 | MOHAMMAD ESMAILI |
| Issued | 11/30/2022 | APPLICANT |
| CofO in Progress | 6/14/2023 | JOAQUIN GREENOUGH |
| Permit Finaled | 6/21/2023 | RONALD MYRICK |
| Permit Finaled | 6/21/2023 | RONALD MYRICK |
| CofO Issued | 6/21/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 8/12/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 10/12/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/13/2022 | CHRISTOPHER ROCHA |
| GPI Written Notices | Cleared | 11/7/2022 | MOHAMMAD ESMAILI |
| Grading Pre-Inspection | Cleared | 11/7/2022 | MOHAMMAD ESMAILI |
| Disturb/Remove Protected Trees | Cleared | 11/29/2022 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/27/2023 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/2/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 2/3/2023 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 3/30/2023 | Conditional Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/31/2023 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2023 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 3/31/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 3/31/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 3/31/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/3/2023 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 4/3/2023 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/3/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 4/3/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/6/2023 | Corrections Issued | CRAIG VAUGHAN |
| Insulation | 4/6/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 4/6/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/6/2023 | Corrections Issued | CRAIG VAUGHAN |
| Shower Pan | 4/6/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/7/2023 | Conditional Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/7/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 4/11/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Insulation | 4/11/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/11/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Shower Pan | 4/11/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 4/11/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Drywall Nailing | 4/14/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 4/14/2023 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 4/14/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Sewer | 4/19/2023 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 4/28/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 5/26/2023 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 5/26/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 5/26/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 5/26/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/30/2023 | Approved | CRAIG VAUGHAN |
| Final | 5/30/2023 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/30/2023 | Approved | CRAIG VAUGHAN |
| Green Building Final | 5/30/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 5/30/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/30/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 5/30/2023 | Approved | CRAIG VAUGHAN |
| Final | 6/13/2023 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Service/Power Release | 6/13/2023 | Approved | JOAQUIN GREENOUGH |