5158 N LOLETA AVE 90041

Certificate Information: 5158 N LOLETA AVE 90041

Application / Permit
22014-20000-02800
Plan Check / Job No.
B22VN08875
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 2-STORY ACCESSORY DWELLING UNIT AND STORAGE TO (E) GARAGE per LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 11/30/2022
Issuing Office
Valley
Current Status
CofO Issued on 6/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 MOHAMMAD ESMAILI
Corrections Issued 7/10/2022 MOHAMMAD ESMAILI
Quality Review Completed 7/21/2022 OMID HEDAYAT
Building Plans Picked Up 7/22/2022 APPLICANT
Applicant returned to address corrections 11/7/2022 MOHAMMAD ESMAILI
Plan Check Approved 11/30/2022 MOHAMMAD ESMAILI
Issued 11/30/2022 APPLICANT
CofO in Progress 6/14/2023 JOAQUIN GREENOUGH
Permit Finaled 6/21/2023 RONALD MYRICK
Permit Finaled 6/21/2023 RONALD MYRICK
CofO Issued 6/21/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 8/9/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 8/12/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 8/12/2022 CHRISTOPHER ROCHA
Low Impact Development Cleared 10/12/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/13/2022 CHRISTOPHER ROCHA
GPI Written Notices Cleared 11/7/2022 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 11/7/2022 MOHAMMAD ESMAILI
Disturb/Remove Protected Trees Cleared 11/29/2022 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/27/2023 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 2/2/2023 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 2/3/2023 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Corrections Issued JOAQUIN GREENOUGH
Deputy Wood Construction 3/30/2023 Conditional Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/31/2023 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/31/2023 Partial Approval CRAIG VAUGHAN
HVAC-Rough 3/31/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 3/31/2023 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 3/31/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 4/3/2023 Approved BRIAN SULLIVAN
HVAC-Rough 4/3/2023 Approved BRIAN SULLIVAN
PLUMBING-Rough 4/3/2023 Not Ready for Inspection BRIAN SULLIVAN
Wood Frame 4/3/2023 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 4/6/2023 Corrections Issued CRAIG VAUGHAN
Insulation 4/6/2023 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 4/6/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 4/6/2023 Corrections Issued CRAIG VAUGHAN
Shower Pan 4/6/2023 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 4/7/2023 Conditional Approval CRAIG VAUGHAN
PLUMBING-Rough 4/7/2023 Approved CRAIG VAUGHAN
Drywall Nailing 4/11/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Insulation 4/11/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/11/2023 Partial Approval ALIZAH MAYAGOITIA
Shower Pan 4/11/2023 Approved ALIZAH MAYAGOITIA
Underground Mechanical 4/11/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Drywall Nailing 4/14/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 4/14/2023 Approved CRAIG VAUGHAN
Underground Mechanical 4/14/2023 Not Ready for Inspection CRAIG VAUGHAN
Sewer 4/19/2023 Approved CRAIG VAUGHAN
Underground Mechanical 4/28/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 5/26/2023 Corrections Issued CRAIG VAUGHAN
Gas Test 5/26/2023 Approved CRAIG VAUGHAN
HVAC-Final 5/26/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 5/26/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 5/30/2023 Approved CRAIG VAUGHAN
Final 5/30/2023 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 5/30/2023 Approved CRAIG VAUGHAN
Green Building Final 5/30/2023 Approved CRAIG VAUGHAN
Green Building Rough 5/30/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/30/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 5/30/2023 Approved CRAIG VAUGHAN
Final 6/13/2023 OK to Issue CofO JOAQUIN GREENOUGH
Service/Power Release 6/13/2023 Approved JOAQUIN GREENOUGH