4627 N WHITE OAK AVE 91316

Certificate Information: 4627 N WHITE OAK AVE 91316

Application / Permit
22014-20000-02783
Plan Check / Job No.
B22VN08814
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Proposed addition and remodel at first floor of (E) single family dwelling.
Permit Issued
Issued on 7/14/2022
Issuing Office
Metro
Current Status
Issued on 7/14/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/7/2022 APPLICANT
Assigned to Plan Check Engineer 6/8/2022 HAYATO TSUCHIYA
Corrections Issued 6/8/2022 HAYATO TSUCHIYA
Building Plans Picked Up 6/8/2022 APPLICANT
Applicant returned to address corrections 7/6/2022 CRISTINA SALAZAR
Plan Check Approved 7/14/2022 ADAM HEGAZI
Issued 7/14/2022 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/16/2022 MANUEL TEJADA
Eng Process Fee Ord 176,300 Cleared 7/7/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/7/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/20/2022 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 9/20/2022 Corrections Issued VINCENT HANLEY
Green Building Rough 9/20/2022 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 10/20/2022 Approved VINCENT HANLEY
PLUMBING-Rough 10/20/2022 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 12/5/2022 Approved VINCENT HANLEY
PLUMBING-Rough 12/5/2022 Partial Approval VINCENT HANLEY
Rough-Elec/Plmb/HVAC 2/14/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/17/2023 Partial Approval VINCENT HANLEY
Gas Test 3/17/2023 Approved VINCENT HANLEY
Insulation 3/17/2023 Approved VINCENT HANLEY
PLUMBING-Rough 3/17/2023 Approved VINCENT HANLEY
Drywall Nailing 4/5/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Approved VINCENT HANLEY
Insulation 4/5/2023 Partial Approval VINCENT HANLEY
Shower Pan 4/5/2023 Approved VINCENT HANLEY
Special/Order Compliance 4/5/2023 Partial Inspection MORRIS JACKSON
Interior/Exterior Lathing 4/18/2023 Partial Approval VINCENT HANLEY
Special/Order Compliance 4/18/2023 Partial Inspection MORRIS JACKSON
BUILDING-Rough-Frame 7/14/2023 Approved VINCENT HANLEY
Green Building Rough 7/14/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/14/2023 Partial Approval HENRY KIM
Special/Order Compliance 8/14/2023 Corrections Issued HENRY KIM
Excavation/Setback/Form/Re-Bar 10/30/2024 Partial Approval THOMAS FINNILA
Wood Frame 10/30/2024 Corrections Issued THOMAS FINNILA
Drywall Nailing 12/3/2024 Partial Approval JOHN COLEMAN