8205 N GENTRY AVE 91605
Certificate Information: 8205 N GENTRY AVE 91605
- Application / Permit
- 22014-20000-02757
- Plan Check / Job No.
- B22VN08716
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERT EXISTEN GARAGE DETACHED IN TO ADU WITH ADDITION AT REAR(77SF) per LAMC 12.22 A33(c) AND (d)
- Permit Issued
- Issued on 8/26/2022
- Issuing Office
- Current Status
- CofO Issued on 3/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2022 | DANIEL SANJUAN |
| Corrections Issued | 6/11/2022 | DANIEL SANJUAN |
| Plan Check Approved | 8/26/2022 | DANIEL SANJUAN |
| Issued | 8/26/2022 | APPLICANT |
| CofO in Progress | 2/29/2024 | MATTHEW NELSON |
| Permit Finaled | 3/8/2024 | RUBEN SALAS |
| Permit Finaled | 3/8/2024 | RUBEN SALAS |
| CofO Issued | 3/8/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/13/2022 | JOSE DUARTE-DIAZ |
| Address approval | Cleared | 6/30/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 7/6/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 8/23/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/23/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 9/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 12/6/2022 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 12/6/2022 | Partial Approval | MATTHEW NELSON |
| Sewer | 12/6/2022 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/23/2023 | Partial Approval | MATTHEW NELSON |
| Sewer | 1/23/2023 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 4/10/2023 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 5/16/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 5/22/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/22/2023 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/25/2023 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 8/25/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 9/21/2023 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Rough | 9/21/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 9/21/2023 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 9/21/2023 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 10/11/2023 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/11/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/11/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Drywall Nailing | 11/3/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 11/3/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Shower Pan | 11/3/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 11/9/2023 | Partial Approval | THOMAS FINNILA |
| Final | 1/31/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 1/31/2024 | Approved | MATTHEW NELSON |
| Final | 2/28/2024 | OK to Issue CofO | MATTHEW NELSON |