6530 N LANGDON AVE 91406
Certificate Information: 6530 N LANGDON AVE 91406
- Application / Permit
- 22014-20000-02746
- Plan Check / Job No.
- B22VN08706
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) (12' x 18'-1") CHICKEN HOUSE & ADD (N) (34'-10" x 18'-10") TO CREATE A 46'-10" X 18'-1" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) (d). WORK PER WFPP
- Permit Issued
- Issued on 11/9/2022
- Issuing Office
- Valley
- Current Status
- Issued on 11/9/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | TROY DEGUZMAN |
| Corrections Issued | 7/6/2022 | TROY DEGUZMAN |
| Quality Review Completed | 7/12/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 7/13/2022 | APPLICANT |
| Applicant returned to address corrections | 10/12/2022 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 11/7/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 11/9/2022 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/9/2022 | ROGELIO CORTES |
| Address approval | Cleared | 8/10/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/10/2022 | DAGOVERTO GUERRERO |
| CPC | Cleared | 8/11/2022 | MIGUEL GAMBOA |
| Construction within easement | Cleared | 8/11/2022 | WALTER RAMIREZ |
| ZI | Cleared | 8/11/2022 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/18/2022 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 10/12/2022 | TROY DEGUZMAN |
| Hydrant and Access approval | Cleared | 10/14/2022 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/13/2023 | Partial Inspection | RYAN SALAZAR |
| Gas Test | 7/18/2023 | Partial Approval | RYAN SALAZAR |
| Sewer | 7/18/2023 | Approved | RYAN SALAZAR |
| Underground Mechanical | 7/21/2023 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 7/24/2023 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 8/3/2023 | Not Ready for Inspection | DAVID MATSON |
| Green Building Rough | 8/3/2023 | Not Ready for Inspection | DAVID MATSON |
| Wood Frame | 8/3/2023 | Approved | DAVID MATSON |
| ELECTRICAL-Final | 8/10/2023 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 8/10/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 8/10/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 8/10/2023 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 8/10/2023 | Approved | RYAN SALAZAR |
| Insulation | 8/15/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 8/24/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 8/24/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/6/2023 | Approved | RYAN SALAZAR |
| Final | 10/6/2023 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 10/6/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 10/6/2023 | Approved | RYAN SALAZAR |
| Final | 11/2/2023 | Not Ready for Inspection | RYAN SALAZAR |