12300-12302 N LITHUANIA DR 91344
Certificate Information: 12300-12302 N LITHUANIA DR 91344
- Application / Permit
- 22014-20000-02739
- Plan Check / Job No.
- B22VN08673
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ECPC: 26'4" X 10'5" ADDITION TO THE (E) SFD, WITH AN INTERIOR REMODEL, AND 18'1" X 5'3" ADDITION TO THE (E) ATTACHED GARAGE AND CONVERT TO A (N) 432 SF ACCESSORY DWELLING UNIT. PER LAMC 12.22 A.33 (c) and (e). ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 7/15/2022
- Issuing Office
- Current Status
- CofO Issued on 3/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 6/6/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 7/8/2022 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 7/12/2022 | APPLICANT |
| Issued | 7/15/2022 | APPLICANT |
| CofO in Progress | 2/28/2023 | STEVEN BACK |
| CofO Issued | 3/1/2023 | JOHN JANSON |
| Permit Finaled | 3/1/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2022 | CHRIS CHAHBAZ |
| Roof/Waste drainage to street | Cleared | 6/9/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 6/9/2022 | CHRIS CHAHBAZ |
| Grading Pre-Inspection | Cleared | 6/13/2022 | MANUEL TEJADA |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | CHRIS CHAHBAZ |
Contact Information
| Contractor | William Brothers Building & Construction; Lic. No.: 1063461-B | 15720 VENTURA BLVD SUITE 616 ENCINO, CA 91436 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/21/2022 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 10/21/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 11/14/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 11/14/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Approved | DAVID SCANTLIN |
| Green Building Rough | 11/14/2022 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 11/14/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 11/14/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Wood Frame | 11/14/2022 | Partial Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 11/18/2022 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 11/18/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 11/18/2022 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 11/30/2022 | Approved | JUSTIN HAWLEY |
| Insulation | 11/30/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 11/30/2022 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 2/13/2023 | Not Ready for Inspection | STEVEN BACK |
| Final | 2/13/2023 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 2/13/2023 | Approved | STEVEN BACK |
| Green Building Final | 2/13/2023 | Approved | STEVEN BACK |
| HVAC-Final | 2/13/2023 | Approved | STEVEN BACK |
| PLUMBING-Final | 2/13/2023 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 2/13/2023 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 2/13/2023 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 2/24/2023 | Approved | STEVEN BACK |
| Final | 2/24/2023 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 2/24/2023 | SGSOV Not Ready | STEVEN BACK |
| Final | 2/28/2023 | OK to Issue CofO | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Approved | STEVEN BACK |