815-817 1/2 W 97TH ST 90044

Certificate Information: 815-817 1/2 W 97TH ST 90044

Application / Permit
22014-20000-02735
Plan Check / Job No.
B22VN08642
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED 7'-8" x 22'-0" ADDITION TO AND CONVERT 18'-4" x 22'-0" PORTION OF (E) 18'-4" x 28'-6" DETACHED RECREATION ROOM INTO A NEW 26'-0" x 22'-0" ACCESSORY DWELLING UNITS PER LAMC 12.22A.33(c) & (e) WITH 26'-0" x 16'-6" IRREGULAR SHAPED ADDITION TO AND CONVERT REMAINING 18'-4" x 6'-6" PORTION OF THE RECREATION ROOM INTO A NEW 16'-6" x 26'-0" DWELLING UNIT TO BE ATTACHED TO THE EXISTING DWELLING TO CREATE A 'DUPLEX' WITH ACCESSORY DWELLING UNIT. ALL WORK PER ENGR. SEE COMMENTS.
Permit Issued
Issued on 10/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2022 APPLICANT
Assigned to Plan Check Engineer 6/3/2022 HAYATO TSUCHIYA
Corrections Issued 6/4/2022 HAYATO TSUCHIYA
Building Plans Picked Up 6/7/2022 APPLICANT
Applicant returned to address corrections 10/20/2022 SARKIS HARABEDIAN
Plan Check Approved 10/25/2022 MIROOSH KHACHATOORIAN
Issued 10/28/2022 APPLICANT
CofO in Progress 9/19/2023 JAMES CHAVEZ
CofO Issued 9/21/2023 ANSON MAGLASANG
Permit Finaled 9/21/2023 ANSON MAGLASANG

Permit Application Clearance Information

Tenant Habitability Plan Cleared 6/13/2022 MICHAEL SOTO
Address approval Cleared 8/18/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 8/18/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/22/2022 TREVOR QUAN
Sewer availability Cleared 8/22/2022 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Chatsky,, German; Lic. No.: C84153 3876 HUNTERS GROVE CT      MOORPARK, CA 93021

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/3/2022 Not Ready for Inspection JOHN KLARIN
Sewer 11/3/2022 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 12/12/2022 Not Ready for Inspection JAMES CHAVEZ
Sewer 12/12/2022 Approved JAMES CHAVEZ
Underground Mechanical 12/12/2022 Approved JAMES CHAVEZ
Footing/Foundation/Slab 12/19/2022 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 3/9/2023 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 3/9/2023 Corrections Issued JAMES CHAVEZ
Green Building Rough 3/9/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Rough 3/9/2023 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Rough 3/9/2023 Approved JAMES CHAVEZ
Green Building Rough 4/3/2023 Approved JAMES CHAVEZ
Insulation 4/5/2023 Approved JAMES CHAVEZ
Drywall Nailing 4/11/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 4/11/2023 Approved JAMES CHAVEZ
Pre-Inspection 7/7/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 7/24/2023 Approved JAMES CHAVEZ
Final 7/24/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 7/24/2023 Not Ready for Inspection JAMES CHAVEZ
Reinforced Masonry Frame 7/24/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 7/24/2023 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 7/24/2023 Approved JAMES CHAVEZ
Final 8/21/2023 OK to Issue CofO JAMES CHAVEZ
Green Building Final 8/21/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 8/21/2023 SGSOV Approved JAMES CHAVEZ
Service/Power Release 8/29/2023 Approved JAMES CHAVEZ