7252 N CLEON AVE 91352

Certificate Information: 7252 N CLEON AVE 91352

Application / Permit
22014-20000-02732
Plan Check / Job No.
B22VN08619
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO THE (E) 1-STORY SFD w/att GARAGE.
Permit Issued
Issued on 10/31/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2022 APPLICANT
Assigned to Plan Check Engineer 6/3/2022 ARTIN ZARUKIAN
Corrections Issued 6/4/2022 ARTIN ZARUKIAN
Building Plans Picked Up 6/9/2022 APPLICANT
Applicant returned to address corrections 10/19/2022 KHUONG TRUONG
Plan Check Approved 10/28/2022 MINA HABILI
Issued 10/31/2022 APPLICANT
CofO in Progress 7/8/2025 RAUL OLAGI
CofO Issued 7/30/2025 RUBEN SALAS
Permit Finaled 7/30/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/10/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 6/14/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/26/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 4/27/2023 Corrections Issued JOHN HAYES
Pre-Inspection 5/3/2023 Approved THOMAS FINNILA
BUILDING-Rough-Frame 6/2/2023 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/2/2023 Corrections Issued JOHN HAYES
Green Building Rough 6/2/2023 No Access for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/12/2023 Approved JOHN HAYES
Green Building Rough 6/12/2023 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 6/12/2023 Approved JOHN HAYES
Insulation 6/20/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 6/20/2023 Approved THOMAS FINNILA
Drywall Nailing 6/28/2023 Approved JOHN HAYES
Final 6/5/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 6/5/2024 Approved JOSE AVILA
Green Building Final 6/5/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 6/5/2024 SGSOV Approved JOSE AVILA
Smoke Detectors 6/5/2024 Not Ready for Inspection JOSE AVILA
Final 6/12/2024 Corrections Issued JOSE AVILA
Smoke Detectors 6/12/2024 Corrections Issued JOSE AVILA
Final 9/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 9/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 9/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 7/8/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ