7252 N CLEON AVE 91352
Certificate Information: 7252 N CLEON AVE 91352
- Application / Permit
- 22014-20000-02732
- Plan Check / Job No.
- B22VN08619
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION TO THE (E) 1-STORY SFD w/att GARAGE.
- Permit Issued
- Issued on 10/31/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 6/4/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/9/2022 | APPLICANT |
| Applicant returned to address corrections | 10/19/2022 | KHUONG TRUONG |
| Plan Check Approved | 10/28/2022 | MINA HABILI |
| Issued | 10/31/2022 | APPLICANT |
| CofO in Progress | 7/8/2025 | RAUL OLAGI |
| CofO Issued | 7/30/2025 | RUBEN SALAS |
| Permit Finaled | 7/30/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/10/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/26/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 4/27/2023 | Corrections Issued | JOHN HAYES |
| Pre-Inspection | 5/3/2023 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/2/2023 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 6/2/2023 | No Access for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 6/12/2023 | Approved | JOHN HAYES |
| Green Building Rough | 6/12/2023 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 6/12/2023 | Approved | JOHN HAYES |
| Insulation | 6/20/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 6/20/2023 | Approved | THOMAS FINNILA |
| Drywall Nailing | 6/28/2023 | Approved | JOHN HAYES |
| Final | 6/5/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 6/5/2024 | Approved | JOSE AVILA |
| Green Building Final | 6/5/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 6/5/2024 | Not Ready for Inspection | JOSE AVILA |
| Final | 6/12/2024 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 6/12/2024 | Corrections Issued | JOSE AVILA |
| Final | 9/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 9/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 9/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 7/8/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |