10554 1/2 W LANARK ST 91352

Certificate Information: 10554 1/2 W LANARK ST 91352

Application / Permit
22014-20000-02706
Plan Check / Job No.
B22VN08538
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
34'-0" X 29'-0" ADDITION OF ACCESSORY DWELLING UNIT TO EXISTING DETACHED GARAGE PER (1,200 SF max per Ordinance, LAMC 12.22 A.33(c) AND (d)) - ALL WORK PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 9/20/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2022 APPLICANT
Assigned to Plan Check Engineer 6/3/2022 DANIEL ABRAMYAN
Corrections Issued 6/4/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 9/19/2022 JESSE ARELLANO
Plan Check Approved 9/19/2022 AUNG SOE
Building Plans Picked Up 9/19/2022 APPLICANT
Issued 9/20/2022 APPLICANT
CofO in Progress 7/13/2023 DAVID ANDERSON
CofO Issued 8/10/2023 RUBEN SALAS
Permit Finaled 8/10/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/20/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/20/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 7/21/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 9/19/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/3/2022 Corrections Issued DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 11/10/2022 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 11/10/2022 Partial Approval DAVID ANDERSON
Deputy Drilled-In Anchors 11/17/2022 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 11/17/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 12/29/2022 Approved DAVID ANDERSON
PLUMBING-Rough 12/29/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/3/2023 Approved DAVID ANDERSON
Green Building Rough 1/3/2023 Approved DAVID ANDERSON
HVAC-Rough 1/3/2023 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 1/13/2023 Approved DAVID ANDERSON
HVAC-Rough 1/27/2023 Approved DAVID ANDERSON
Shower Pan 1/27/2023 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 2/3/2023 Approved DAVID ANDERSON
Insulation 2/3/2023 Approved DAVID ANDERSON
Shower Pan 2/3/2023 Approved DAVID ANDERSON
Drywall Nailing 2/13/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 2/13/2023 Partial Approval DAVID ANDERSON
Underground Mechanical 2/13/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 2/16/2023 Approved DAVID ANDERSON
ELECTRICAL-Final 4/7/2023 Not Ready for Inspection DAVID ANDERSON
Final 4/7/2023 Corrections Issued DAVID ANDERSON
Green Building Final 4/7/2023 Approved DAVID ANDERSON
HVAC-Final 4/7/2023 Approved DAVID ANDERSON
PLUMBING-Final 4/7/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 4/7/2023 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 4/7/2023 Approved DAVID ANDERSON
Final 7/10/2023 OK to Issue CofO DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 7/10/2023 SGSOV Approved DAVID ANDERSON