5822 N LUBAO AVE 91367
Certificate Information: 5822 N LUBAO AVE 91367
- Application / Permit
- 22014-20000-02702
- Plan Check / Job No.
- B22VN08527
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ENTIRE SFD W/ ATTACHED GARAGE EXCEPT SOUTH 14LF WALL & FOOTING & ADD 1-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/4/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 8/8/2022 | STEVEN KIM |
| Building Plans Picked Up | 8/19/2022 | APPLICANT |
| Applicant returned to address corrections | 2/24/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/1/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/8/2023 | NILOOFAR MEHRAIN |
| Issued | 3/17/2023 | APPLICANT |
| CofO in Progress | 5/29/2024 | JON MCHUGH |
| CofO in Progress | 7/8/2024 | SEAN WIRCH |
| Permit Finaled | 8/7/2024 | JOHN JANSON |
| CofO Issued | 8/7/2024 | JOHN JANSON |
| Permit Finaled | 8/7/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/5/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 2/10/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 2/28/2023 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 3/14/2023 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 3/14/2023 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 3/14/2023 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 3/14/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/10/2023 | No Access for Inspection | EMIL ALEXANDRIAN |
| Underground Mechanical | 4/13/2023 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 4/27/2023 | Approved | JON MCHUGH |
| Deputy Wood Construction | 6/30/2023 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Approved | JEFFREY BULL |
| Wood Frame | 6/30/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 7/5/2023 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 7/5/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 7/5/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 7/10/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 7/10/2023 | Approved | JON MCHUGH |
| Shower Pan | 7/10/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 7/12/2023 | Not Ready for Inspection | JON MCHUGH |
| Shower Pan | 7/12/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 7/17/2023 | Partial Approval | JOHN KIDWELL |
| Wood Frame | 7/17/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Wood Frame | 7/18/2023 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 7/20/2023 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 7/20/2023 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 7/20/2023 | Corrections Issued | JUSTIN HAWLEY |
| HVAC-Rough | 7/20/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 7/20/2023 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 7/26/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 8/17/2023 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 9/8/2023 | Partial Approval | JON MCHUGH |
| Underground Mechanical | 9/8/2023 | Partial Approval | JON MCHUGH |
| Underground Mechanical | 10/25/2023 | Partial Approval | JON MCHUGH |
| Gas Test | 3/11/2024 | Approved | JON MCHUGH |
| HVAC-Final | 3/11/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 3/11/2024 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 3/11/2024 | SGSOV Approved | JON MCHUGH |
| Final | 5/13/2024 | Corrections Issued | JON MCHUGH |
| HVAC-Final | 5/13/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 5/13/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 5/20/2024 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Final | 5/21/2024 | Corrections Issued | JON MCHUGH |
| Final | 5/21/2024 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 5/24/2024 | Approved | JON MCHUGH |
| Final | 5/24/2024 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 5/24/2024 | Approved | JON MCHUGH |
| Green Building Rough | 5/24/2024 | Approved | JON MCHUGH |
| Smoke Detectors | 5/24/2024 | Approved | JON MCHUGH |
| Final | 5/29/2024 | OK to Issue CofO | JON MCHUGH |