20126 W TUBA ST 91311
Certificate Information: 20126 W TUBA ST 91311
- Application / Permit
- 22014-20000-02699
- Plan Check / Job No.
- B22VN08516
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF KITCHEN, REPLACE WINDOW, AND ADDITION OF 14'-11" x 8'-9" TO (E) PER ENGINEERING
- Permit Issued
- Issued on 7/29/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2022 | ALFRED RAMIREZ |
| Corrections Issued | 6/6/2022 | ALFRED RAMIREZ |
| Plan Check Approved | 6/30/2022 | ALFRED RAMIREZ |
| Building Plans Picked Up | 7/6/2022 | APPLICANT |
| Issued | 7/29/2022 | APPLICANT |
| CofO in Progress | 1/19/2023 | DAVID SCANTLIN |
| Permit Finaled | 3/10/2023 | DANIEL ORRANTE |
| CofO Issued | 3/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 6/25/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 6/25/2022 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 6/25/2022 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 6/25/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Agazaryan Anet; Lic. No.: 1069702-B | 6802 ESTAPA DRIVE TUJUNGA, CA 91042 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/3/2022 | Partial Approval | JEFFREY PARD |
| Deputy Drilled-In Anchors | 8/9/2022 | Conditional Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 8/15/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 10/12/2022 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 10/12/2022 | Partial Approval | JOHN KIDWELL |
| Rough-Elec/Plmb/HVAC | 10/12/2022 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 10/20/2022 | Partial Approval | JOHN KIDWELL |
| Insulation | 11/7/2022 | No Access for Inspection | KRISTEN CAUSEY |
| Deputy Drilled-In Anchors | 11/8/2022 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 11/14/2022 | Approved | JUSTIN HAWLEY |
| Insulation | 11/14/2022 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 11/14/2022 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Approved | JOHN KIDWELL |
| Drywall Nailing | 11/30/2022 | Approved | KRISTEN CAUSEY |
| Green Building Rough | 11/30/2022 | Approved | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 1/12/2023 | SGSOV Not Ready | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 1/17/2023 | Approved | DAVID SCANTLIN |
| Final | 1/17/2023 | OK to Issue CofO | DAVID SCANTLIN |
| Footing/Foundation/Slab | 1/17/2023 | Approved | DAVID SCANTLIN |
| Green Building Final | 1/17/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 1/17/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 1/17/2023 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 1/17/2023 | Partial Inspection | MORRIS JACKSON |