7455-7457 N OSTROM AVE 91406
Certificate Information: 7455-7457 N OSTROM AVE 91406
- Application / Permit
- 22014-20000-02694
- Plan Check / Job No.
- B22VN08502
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF CARPORT TO ADU AND THE REMAINING PORTION OF THE CARPORT TO (E) SFD
- Permit Issued
- Issued on 9/19/2022
- Issuing Office
- Current Status
- CofO Issued on 5/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2022 | FERNANDO FLORES |
| Corrections Issued | 6/14/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 7/12/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 7/21/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 8/6/2022 | FERNANDO FLORES |
| Plan Check Approved | 9/14/2022 | RAHEL BEYENE |
| Issued | 9/19/2022 | APPLICANT |
| CofO in Progress | 5/19/2023 | RAUL OLAGI |
| Permit Finaled | 5/23/2023 | MICHAEL SMITH |
| CofO Issued | 5/23/2023 | MICHAEL SMITH |
| Permit Finaled | 5/23/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2022 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2022 | CHRIS CHAHBAZ |
| Roof/Waste drainage to street | Cleared | 8/31/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 8/31/2022 | CHRIS CHAHBAZ |
| Public Works-Highway Ded. | Cleared | 9/14/2022 | ROMAN GUTIERREZ |
| Public Works-Open Permits | Cleared | 9/14/2022 | ROMAN GUTIERREZ |
| Public Works-Sewers | Cleared | 9/14/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/31/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 12/19/2022 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 12/28/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/20/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 1/20/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 1/20/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 1/20/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 2/2/2023 | Approved | RAUL OLAGI |
| Shower Pan | 3/3/2023 | Approved | RAUL OLAGI |
| Final | 5/1/2023 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 5/1/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 5/1/2023 | Approved | RAUL OLAGI |
| Final | 5/19/2023 | OK to Issue CofO | RAUL OLAGI |